Direct, Monitor, and Control Project Work (PMBOK® Guide Fifth Edition)

Course Overview

Read the Course Overview.

Direct and Manage Project Work

Monitor and Control Project Work

Course Overview

Imagine setting off on a voyage across the ocean in a ship that has no electronic or satellite navigation system on board. None of the crew members seem concerned by this as they go about their duties and the journey proceeds. At first, you enjoy clear skies and are making good headway towards your destination.

However, before long, dark clouds roll in and blot out the sky. Strong winds begin to blow the ship off course. But how far off course?

And how will the captain steer the ship accurately without a way to orient the ship to its destination?

Most projects aren't lucky enough to enjoy smooth sailing from beginning to end. Unforeseen events and difficulties usually crop up somewhere along the line, and these can steer a project off course. Thankfully, there are many proven project management processes designed to direct, monitor, and control project work.

For example, the establishment of project baselines for schedule, cost, and scope give the project manager a clear destination to steer toward.

When problems arise, strategies for managing changes help get the project back in line.

Question

What approach do you think project managers should take when they're ready to execute a project? Consider the following view, "If I've planned the project well, I can relax and rely on the plan to guide everyone to get the job done."

Do you agree or disagree with this approach?

Options:

  1. Agree
  2. Not sure
  3. Disagree

Answer

Option 1: As a project manager, your job is like that of an orchestra conductor. You can't just hand over the music and hope for the best. In the same way the conductor guides the orchestra, you must guide your team to ensure that tasks are done on time and correctly.

Option 2: One of the responsibilities of a project manager is to ensure that a project is planned well. But that's not where the responsibility ends. A project manager must closely monitor the progress of a project when it's executed. Sometimes it may be necessary to take precautionary measures, repair damage, or revise deliverables to get the project back on track if it veers off course.

Option 3: It's not enough for a project manager to pass on a good plan to the project team and expect the project to proceed as planned. It's necessary to oversee the project as it's executed, and to perform activities to monitor and control project work.

Question

Now consider this approach to dealing with problems that arise when a project is being executed: "There's no point dwelling on the negative – we just have to fix the problems quickly and move on."

Do you agree or disagree with this statement?

Options:

  1. Agree
  2. Not sure
  3. Disagree

Answer

Option 1: Of course you need to resolve problems quickly, but you also need to manage changes carefully. So it's not just a question of moving along swiftly. Integrated change control will enable you to manage change without overlooking its impact on particular areas of a project.

Option 2: There's a difference between dwelling on the negative and ensuring an issue is correctly dealt with. By using integrated change control, you can manage the corrective or preventive actions necessary to get your project back on track.

Option 3: It's true that using a quick fix to deal with problems is not a wise strategy. The best way to deal with issues is by using integrated change control to manage necessary changes carefully.

So you've initiated and planned your project. It's now time to direct and manage all aspects of the project's delivery. The project work needs to be carefully monitored and controlled if you're to meet project objectives.

In this course, you'll learn about the activities involved in directing and managing the work of a project. You'll learn about the inputs that help you in this process. You'll also learn about the tools and techniques you can use to direct and manage a project, and the outputs resulting from this process.

Graphic

Figure 4-6 of the PMBOK® Guide, Fifth Edition shows the inputs are the project management plan, approved change requests, enterprise environmental factors, and organizational process assets. The tools and techniques are expert judgment, project management information system, and meetings. The outputs are deliverables, work performance data, change requests, project management plan updates, and project documents updates.

In addition, this course will show you how to monitor and control project work to ensure work performance is in line with requirements. You'll also learn about updating project baselines.

As well as helping you understand how to execute and complete projects, this course will show you how to learn from your experiences so that your project management expertise continues to grow.

Back to top

Inputs to Directing and Managing Project Work

Learning Objectives

After completing this topic, you should be able to

1. Direct and manage project execution

Creating a project management plan is one thing. Executing it is another. There are no guarantees that your project will follow the exact course of your plan.

The Direct and Manage Project Work process is what you use to carry out the work identified in the project management plan, so that the objectives of a project are met.

During this process, the project manager oversees the execution of tasks by the project team needed to create the project deliverables.

So as a project manager, you need to be flexible and ready for contingencies.

As Norman Vincent Peale, the motivational speaker, said, "Plan your work for today and every day, then work your plan." A project manager must know how to work a plan.

The Direct and Manage Project Work process falls within the Project Integration Management Knowledge Area.

Graphic

Table 3-1 of the PMBOK Guide Fifth Edition shows that other processes in the Project Integration Management Knowledge Area include Develop Project Charter which is an Initiating process, Develop Project Management Plan which is a Planning process, Monitor and Control Project Work and Perform Integrated Change Control which are Monitoring and Controlling processes, and Close Project or Phase which is a Closing process.

And because Project Integration Management is all about integrating the different aspects of a project, the activities that make up the Direct and Manage Project Work process span across other Knowledge Areas.

Select each Knowledge Area to find out what activities fit into it.

Project Quality Management
Implementing process improvements is an activity of the Direct and Manage Project Work process, which is categorized in the Project Quality Management Knowledge Area.
Project Human Resource Management
Activities in the Project Human Resource Management Knowledge Area that are part of directing and managing project work include assigning, training, and managing the project team members.
Project Communications Management
Establishing and maintaining internal and external communication channels is an activity of the Direct and Manage Project Work process that falls within the Project Communications Management Knowledge Area.
Project Risk Management
Part of directing and managing a project is managing identified risks and executing risk response activities, which are processes that fall in the Project Risk Management Knowledge Area.
Project Procurement Management
Direct and Manage Project Work process activities that relate to the Project Procurement Management Knowledge Area include obtaining and managing the resources that the project team needs.
Project Stakeholder Management
The process of communicating and working with
stakeholders to meet their needs and expectations is also an important part of directing and managing project work.

In addition to fitting into different Knowledge Areas, the activities in the Direct and Manage Project Work process are linked to other processes in the Project Integration Management Knowledge Area. This is because you use the outputs of these activities as inputs for the Monitor and Control Project Work, Perform Integrated Change Control, and Close Project or Phase processes.

Graphic

Table 3-1 of the PMBOK Guide Fifth Edition shows that other processes in the Project Integration Management Knowledge Area include Develop Project Charter which is an Initiating process, and Develop Project Management Plan which is a Planning process.

Direct and Manage Project Work also involves executing changes made to the project management plan, once these changes have been approved.

Graphic

A project management plan may include a section which introduces the project and its purpose, followed by a scope section in which the objectives and deliverables are described.

For example, where corrective actions must be taken to ensure project performance is in line with targets, the Direct and Manage Project Work process is responsible for updating the scope of the project to include this change, and including the necessary actions into the project management plan – such as hiring further staff to ensure an objective is met on time.

Graphic

In hiring additional staff, a project manager would review resumes.

The process can also involve issuing change requests to prevent negative outcomes.

These may be requests to repair product defects reported during the Control Quality process.

So this process ties in with the Project Quality Management Knowledge Area.

The Direct and Manage Project Work process is also responsible for collecting and documenting lessons learned.

For example, a team creating one of the deliverables for a project has consistently been behind schedule. The project manager discovers that no one was tasked with moving the product between two phases of development, which led to delays in forwarding the product.

The project manager now assigns a team member to this task, and the issue is recorded as a lesson learned.

Supplement

Selecting the link title opens the resource in a new browser window.

Job Aid

Access the job aid Direct and Manage Project Work Activities for a list of the activities involved in directing and managing project work.

Question

Although the Direct and Manage Project Work process falls in the Project Integration Management area, it includes activities that span across the other Knowledge Areas.

Match each Direct and Manage Project Work process activity to the Knowledge Area in which it fits.

Options:

  1. Managing the resources to be used by the project team
  2. Adapting the project baseline to reflect approved changes
  3. Managing the project team staff
  4. Implementing activities to reduce potential negative outcomes
  5. Maintaining internal channels for relaying information to stakeholders

Targets:

  1. Project Procurement Management
  2. Project Quality Management
  3. Project Human Resource Management
  4. Project Risk Management
  5. Project Communications Management and Project Stakeholder Management

Answer

Obtaining and managing resources are activities that fall in the Project Procurement Management Knowledge Area.

An activity of Direct and Manage Project Work is submitting change requests and adjusting project scope baselines to reflect approved changes. These continuous improvement activities fall in the Project Quality Management Knowledge Area.

Managing project team staff, including assigning and training the staff, is an activity that relates to the Project Human Resource Management Knowledge Area.

Executing risk responses and managing identified risks are activities related to the Project Risk Management Knowledge Area.

Establishing and maintaining communication channels and ensuring stakeholders are appropriately engaged are activities that fall in the Project Communications and Stakeholder Management Knowledge Areas.

Correct answer(s):

Target 1 = Option A

Target 2 = Option B

Target 3 = Option C

Target 4 = Option D

Target 5 = Option E

The plan for a project to upgrade a processing plant for a chemicals manufacturer is complete.

Graphic

The project management plan for the revamping project specifies the introduction for and the scope of the project.

So the Direct and Manage Project Work process can now go ahead.

The project manager meets with the construction company that's been selected to do the work.

She then chooses an in-house project team who'll be involved in coordinating the project's progress. She's responsible for the team's training requirements and she'll manage the team throughout the project.

She holds a meeting with the members and briefs them about their duties as part of the project team and about their specific tasks. In this way, she establishes the project's communication channels.

One of the key factors affecting the revamping project is the construction schedule. This is because the chemical plant will still be operational while the project is being carried out.

Graphic

The construction schedule table contains headings for ID, Task name, Duration, Start and Finish.

This means that construction tasks must be completed in very precise time frames so that when production processes are halted, it is not for a prolonged period.

Graphic

For example, the specific duration for these tasks are listed as four days, 10 days, two days, and so forth.

While performing activities to direct and manage the project work, the manager keeps this identified risk – the interruption of operations – in mind, and implements risk response activities. She does so by generating work performance information related to scheduling.

As the project progresses, the project manager notices that production is being stopped for longer times than planned. She realizes she needs to make adjustments to the schedule so that production downtime is in line with targets.

Graphic

For example, the first task called remove unit D5 was scheduled to finish on April 10, and the next task called install unit D5A was scheduled to start April 11. The project manager updated the schedule so that task 1 now finishes April 15 and task 2 starts April 16. The remaining dates in the schedule are also updated accordingly.

Once these adjustments are planned and approved, the project manager passes the information to the project team so that the construction processes can be improved accordingly.

This ties in with executing processes to distribute information, which falls within the Project Communications Management Knowledge Area.

Graphic

The specific Executing process is called Manage Communications. Other processes in that Knowledge Area include Plan Communications Management, which is a Planning process, and Control Communications which is a Monitoring and Controlling process.

There is another identified risk that relates to interrupting the production process while construction takes place.

Certain chemicals form the basis of most other products that the plant manufactures. If the production of these chemicals is interrupted, it will have a ripple effect on overall production.

Because of this, and as a risk response activity, the project manager ensures that any revamping of production units involved in producing these essential chemicals is planned very carefully.

The project manager sets up a schedule of regular meetings with the internal project team and the external contractor, which maintains good communication channels between stakeholders throughout the project.

Graphic

For example, the team will meet every Friday at 8:30 or 9:30 a.m.

This activity is associated with the Project Communications Management Knowledge Area, and it helps her keep up to date with progress and any relevant issues.

Graphic

The specific Communications Management process is called Manage Communications.

She also has regular meetings with the plant floor managers to inform them of the construction schedule so they can plan production at their stations accordingly.

The project manager is responsible for procuring resources, such as the specialized equipment, needed for the revamped production units.

This activity relates to obtaining and managing the resources the project team will require – an activity of the Conduct Procurements process.

Graphic

The specific process is called Conduct Procurements and is an Executing process. Other processes in that Knowledge Area include Plan Procurement Management, which is a Planning process, Control Procurements which is a Monitoring and Controlling process, and Close Procurements which is a Closing process.

She's chosen a manufacturing company from several bidders and is in regular contact with the company. She ensures the new equipment is at hand when the construction team is ready to install it.

As the project progresses, the project manager documents lessons learned. One such lesson relates to how, during planning, the team relies on filed documents about the old equipment.

When assessments of the actual equipment are made, the team discovers that the old documentation isn't always accurate.

Graphic

For example, she may record in the lessons learned log Check accuracy of filed documents on old equipment.

After this is discovered, the assessment team becomes more vigilant in its inspections, and the project manager ensures that accurate documentation is created for the new manufacturing units. She records this as a lesson learned.

By performing activities that are part of the Direct and Manage Project Work process, the project manager ensures that the revamping project stays on track.

When problems arise, she deals with them, constantly adjusting the project management plan or taking steps to keep processes in line with it.

So she steers the project while work is executed to make sure the objectives of the project are met.

Question

A company that manufactures office furniture has decided to change its order entry system software.

What are some of the nontechnical activities the project manager would carry out as part of the Direct and Manage Project Work process for this project?

Options:

  1. Increasing the number of software testers
  2. Choosing a chief technical advisor to provide expert advice so there is no misunderstanding about requirements
  3. Ensuring the development team has access to test machines
  4. Gathering information on the progress of the software's development
  5. Testing the software during its development
  6. Developing the document to authorize the rollout of the software

Answer

Option 1: This is a correct option. Assigning more project team staff is an activity in the Direct and Manage Project Work process. In this case, the project manager increases staff to ensure the quality of the work.

Option 2: This option is correct. Part of directing and managing a project involves managing identified risks and executing risk response activities. One of the identified risks is the possibility of the software developers misunderstanding the company's requirements. To manage this risk, the project manager assigns a chief technical advisor. This also relates to the activity of assigning and managing project team staff.

Option 3: This is a correct option. As part of the Direct and Manage Project Work process, the project manager must ensure that the project team has the resources it needs.

Option 4: This option is correct. Generating work performance information is an activity in the Direct and Manage Project Work process. This information will be used to forecast when work will complete.

Option 5: This is an incorrect option. The project manager wouldn't be responsible for performing duties like testing. However, the project manager does assign the staff who will do the testing, which is an activity of the Direct and Manage Project Work process.

Option 6: This option is incorrect. Developing the document that authorizes a phase of the project is part of the Develop Project Charter process. This activity would not be performed during the Direct and Manage Project Work process.

Correct answer(s):

1. Increasing the number of software testers
2. Choosing a chief technical advisor to provide expert advice so there is no misunderstanding about requirements
3. Ensuring the development team has access to test machines
4. Gathering information on the progress of the software's development

2. The inputs

The Direct and Manage Project Work process uses four inputs. These are the project management plan, approved change requests, enterprise environmental factors, and organizational process assets.

The project management plan sets out how a project will be executed, and defines how it should be monitored, controlled, and closed.

As an input to the Direct and Manage Project Work process, it tells the project team how to execute the work to create the project deliverables.

It also sets out how changes must be monitored and controlled. The project manager will need this information when implementing process improvements and when generating the data that will be used to monitor project activities.

The project management plan also provides information on how to sustain performance measurement baselines.

The project manager uses this information to implement process improvements and collect work performance information.

Graphic

Work performance information can be obtained from a budget status report.

Techniques for communicating with stakeholders are also part of the project management plan. In the Direct and Manage Project Work process, the project manager uses this information to establish communication channels.

Approved change requests expand or reduce the scope of a project. They are recorded in the project management plan and subsidiary plans. Sometimes approved change requests call for preventive or corrective actions to be taken. Actions like these are performed during the Direct and Manage Project Work process.

Enterprise environmental factors are conditions surrounding a project, like available resources and market conditions that can influence its success.

There are several enterprise environmental factors that may be used as inputs to the Direct and Manage Project Work process. These include company structure and culture, infrastructure, human resource administration, stakeholder risk tolerance, and project management information systems.

Select each enterprise environmental factor to learn more about how it's an input to the Direct and Manage Project Work process.

Company structure and culture
Company structure and culture influences the way a project is executed because the work must be done within these boundaries. For example, if a company has a complex hierarchy, it may take longer for decisions to be made, whereas a more flat structure may speed up approval processes.

Infrastructure
The infrastructure of the organization – such as its facilities and equipment – provides the means by which the project work is executed.

Human resource administration
Human resource administration provides guidelines for hiring and firing procedures, training, and how to conduct performance reviews. The project manager uses these guidelines when choosing, training, and managing the staff that work on a project.

Stakeholder risk tolerance
During the Direct and Manage Project Work process, the project manager is responsible for managing identified risks and executing risk response activities. The project manager has to factor in the tolerance of stakeholders to risk when doing this. For example, an organization may not have the capacity to risk an impact on its cash flow, so the project manager must be aware of this.

Project management information systems
Project management information systems may include software tools that automate tasks, such as scheduling, gathering information, and creating performance reports. These tools help the project manager generate work performance information to forecast when objectives will be met.

Organizational process assets include the plans, guidelines, policies, and procedures that are used to guide the project work while it's executed.

Recorded knowledge, such as lessons learned and files from previous projects, are also organizational process assets the project manager will use.

Subsidiary plans from prior projects relating to costs, scope, and schedule, quality and performance measurement baselines, and risk registers are some of the files the project manager might use.

Other organizational process assets may be inputs for the Direct and Manage Project Work process:

The project to upgrade processing plant facilities at a chemicals manufacturer uses several inputs, including the project management plan, enterprise environmental factors, organizational process assets, and approved change requests.

Select each input to learn about how the project manager used it.

Project management plan
The project manager uses the project management plan to determine what must be done and to monitor the project as work progresses.
Enterprise environmental factors
To generate data for monitoring the scheduled project work, the project manager uses a software tool to create a report. This tool is an example of an enterprise environmental factor. It helps him determine that some construction tasks are interrupting production for longer than planned.
Approved change request
The project manager submits a change request to adjust the construction schedule. Once this is approved, the change is made to the project management plan. The approved change request then becomes an input for directing and managing project work, and construction work procedures are changed.
Organizational process assets
The project manager makes use of historical data, such as the filed documentation for the old equipment. This data is an organizational process asset. When it's discovered that the data isn't always accurate, the project manager records this as a lesson learned. The record he makes then becomes an organizational process asset.

Question

What are the inputs for the Direct and Manage Project Work process?

Options:

  1. The project management plan
  2. Approved change requests
  3. Infrastructure
  4. Standardized guidelines
  5. The deliverables of the project
  6. Work performance data

Answer

Option 1: This is a correct option. The project management plan specifies how a project will be executed, monitored, controlled, and closed. As an input to the Direct and Manage Project Work process, it informs the project team how to perform the work required, and the project manager of how to monitor and control the project as it's executed.

Option 2: This option is correct. When a change request is approved, the project management plan is updated. If preventive or corrective actions are specified, these must be performed as part of the execution of the project. So approved change requests become inputs to the Direct and Manage Project Work process.

Option 3: This is a correct option. Enterprise environmental factors, such as organizational infrastructure and human resource administration, influence the success of a project. They are inputs to the Direct and Manage Project Work process because they are used when project work is performed.

Option 4: This option is correct. Organizational process assets include policies, plans, and guidelines. They are inputs to the Direct and Manage Project Work process because they are referred to and used to complete project tasks.

Option 5: This is an incorrect option. The Direct and Manage Project Work process creates the project deliverables. These aren't an input to the process.

Option 6: This option is incorrect. Work performance data is not an input to the Direct and Manage Project Work process. Rather, it is an output of project activities that direct and manage execution.

Correct answer(s):

1. The project management plan
2. Approved change requests
3. Infrastructure
4. Standardized guidelines

3. Summary

The Direct and Manage Project Work process involves carrying out the work that's specified in the project management plan so that a project's requirements are met. Some of the activities the project manager performs during this process include managing a project team, establishing and maintaining communication channels, managing risks and implementing risk responses, generating performance data, implementing process improvements, and managing resources.

Inputs to the Direct and Manage Project Work process are the project management plan, approved change requests, enterprise environmental factors, and organizational process assets.

Back to top

Tools for Directing and Managing Project Work

Learning Objective

After completing this topic, you should be able to

1. Exercising expert judgment

Expert judgment and meetings are two of the tools and techniques that a project manager uses to direct and manage the work of a project. Managers might use their own judgment or meet with an expert to consult about the project.

During this process, meetings would be used to discuss and agree on major aspects of directing and managing project work. For example, meeting participants may discuss relevant risks, possible scope changes, cost overruns, or changes to the schedule.

A project manager is overseeing process changes affecting the way the network in a new office was set up. While reviewing work performance information, she notices that the work hasn't been done correctly. A change request is issued and approved.

Select each method to find out how the manager uses it in this situation.

Use own judgment
The project manager uses her own judgment when she arranges a meeting with the IT company that is contracted to do the work to discuss the problems and instruct it how to fix them. She also adjusts the schedule of work to accommodate this.

The project manager knows what to do because she's been the project manager on a previous project that set up the network for the company's office extension.
Meet with an expert
When the project manager doesn't have the knowledge necessary to implement a change request, she consults an expert.

For example, once the approved changes to the network are implemented, the project manager talks to a senior IT technician to find out which elements require testing to ensure the changes are successful.

If the project manager had consulted a colleague who's never tested a network, then she wouldn't have received the expert judgment she needs.

When the project manager has the necessary knowledge and experience, she uses her expert judgment – such as when she draws on her previous experience to implement the approved change request. But in situations where she doesn't have the required knowledge, she consults other people who have expertise in that area and are thus able to exercise their expert judgment.

Possible sources of expert judgment for a project include the project manager, people on the project team, consultants, and members of professional and technical associations. They also include people in other branches of the organization, and stakeholders such as sponsors and customers.

As a project manager, you use expert judgment to assess the inputs of the Direct and Manage Project Work process.

This is what ensures that you interpret and respond to the inputs in a way that aligns to the project management plan, while project work is carried out.

As you will recall, inputs for directing and managing project work are the project management plan, approved change requests, organizational process assets, and enterprise environmental factors.

Select each project manager for an example of how they used expert judgment to assess one of these inputs.

Todd
"On my project, I asked for the advice of a colleague who'd worked on a similar project to mine to get guidance on the technical performance measurements specified in the project management plan."

Michelle
"An organizational restructure at my company affected the composition of the project team I'm managing. I had to consult with our HR Department to assess how to redistribute staff for the project."

Lili
"The project team I'm managing ran into a technical difficulty. When we solved the problem, we recorded the event as a lesson learned. But then the problem happened again! This time, I've consulted technical experts in our organization and we'll use their advice to resolve this issue once and for all."

Todd used the expert judgment of a colleague to get advice on how to execute work specified in the project management plan.

Michelle used the expert judgment of her company's HR Department to assess an enterprise environmental factor – a change in her organization's structure that affected the project she was managing.

Lili used the judgment of her company's technical experts to assess a lesson learned – an organizational process asset – when technical difficulties occurred.

Question

Identify examples where expert judgment and meetings are used to direct and manage project work.

Options:

  1. Lisa needs help implementing a preventive action and consults a technical expert with experience in the area
  2. Simon uses his knowledge of past projects to implement policies to execute project work
  3. Kelly needs some advice on how to implement an approved change so she asks the opinion of a colleague, who has no experience in this area
  4. John consults the project management plan to establish how to sustain performance measurement baselines
  5. Michelle consults a market researcher to determine how current market conditions may affect her project

Answer

Option 1: This option is correct. Lisa makes use of the judgment of a technical expert, who has knowledge and experience that she doesn't, to determine how to implement an approved change request.

Option 2: This is a correct option. Policies are an example of organizational process assets. Simon uses his own expert judgment to assess policies, which are inputs for the Direct and Manage Project Work process. His past experience with other projects enables him to do this.

Option 3: This option is incorrect. Kelly isn't making use of expert judgment when she asks the opinion of a colleague who has no particular knowledge about how to implement a similar change. Expert judgment requires relevant knowledge and experience, which her colleague in this case doesn't have.

Option 4: This is an incorrect option. Although the project management plan is an input for the Direct and Manage Project Work process, it is not a source of expert judgment.

Option 5: This option is correct. Michelle uses the expert judgment of a market researcher to assess an enterprise environmental factor – in this case, market conditions.

Correct answer(s):

1. Lisa needs help implementing a preventive action and consults a technical expert with experience in the area
2. Simon uses his knowledge of past projects to implement policies to execute project work
5. Michelle consults a market researcher to determine how current market conditions may affect her project

2. Project management information systems

In addition to expert judgment and meetings, an important tool for directing and managing project work is a project management information system. This is a system that gathers, records, filters, and disseminates information.

Project managers use various project management information systems to manage project work. These can include a project management program and collaboration software for communicating with the project team and stakeholders, knowledge management software for managing information, an accounting program for retrieving important cost information, and a configuration management system for managing product versions.

Select each type of project management information system to find out how it was used in a project to develop and implement tracking software to manage a company's operations.

Project management program
The project manager uses a project management program to collect data relating to the software's ability to track product demand accurately.

Project management software tools like this help to facilitate the smooth running of a project by providing an organized, searchable repository for all information relating to the project.
Collaboration software
The project manager alerts the Quality Assurance team when she discovers a problem with the software – it overcalculates product demand, which will lead to a surplus of goods stored at the warehouse. She communicates this discovery via collaboration software with e-mail notifications.
Knowledge management software
The project manager uses knowledge management software to post detailed documentation about the findings related to the overcalculation problem. The quality assurance team can then access the information and use it to address the issue.
Accounting program
The project manager uses an accounting program to retrieve cost information to compare the current costs of the project with the budget in the project management plan. There is an inaccuracy relating to the labor cost calculation so the project manager makes adjustments to the budget accordingly.
Configuration management system
As the software is developed and improved, different versions are created. So the project manager uses a configuration management system to track the software as it's developed, and details about its version number, design, functionality, and requirements are documented and up to date.

The project manager can then compile reports using the data she collects from the various information systems she uses while the project is executed. She then keeps stakeholders up to date by using collaboration software to notify them of reports about the project status.

Project management information systems usually have one or more capabilities in common:

Question

What are examples of a project manager using information systems to manage and direct project work?

Options:

  1. Using a project management program to collect data and generate performance reports
  2. Posting information the project team needs on a knowledge management site
  3. E-mailing stakeholders with progress reports
  4. Meeting in person with stakeholders to present progress reports
  5. Providing the project team with hard copies of the project management plan

Answer

Option 1: This is a correct option. A project management program is a type of information system that a project manager can use to collect and process data on the progress of the project.

Option 2: This is a correct option. Knowledge management software are often used to manage and distribute information and resources the project team needs to carry out project work. This type of application is an example of a project management information system.

Option 3: This is a correct option. A project manager uses e-mail through the collaboration tools to disseminate project information to stakeholders.

Option 4: This is an incorrect option. Holding a meeting in person does not make use of a project management information system.

Option 5: This is an incorrect option. Information in hard copy format doesn't classify as making use of an information system. If the project management plan was made available to the team on a knowledge management site, for example, then this would be making use of an information system.

Correct answer(s):

1. Using a project management program to collect data and generate performance reports
2. Posting information the project team needs on a knowledge management site
3. E-mailing stakeholders with progress reports

3. Summary

During the Direct and Manage Project Work process, project managers use expert judgment to assess inputs and manage project work appropriately. They may use their own expert judgment where they have the necessary knowledge, and the expert judgment of others – such as consultants or technical experts.

Project managers also use project management information systems to gather, record, filter, and disseminate information. Examples of these systems include project management programs, collaborative software, knowledge management software, accounting programs, and configuration management systems.

Supplement

Selecting the link title opens the resource in a new browser window.

Follow-on Activity

Access the follow-on activity Using Expert Judgment to assess the way you use experts on projects you manage.

Back to top

Outputs of Directing and Managing Project Work

Learning Objective

After completing this topic, you should be able to

1. The outputs

What you get out is what you put in. The quality of the outputs that are created through the Direct and Manage Project Work process depends on the quality of the work carried out.

These are the outputs that you generate during the Direct and Manage Project Work process:

Deliverables are the outcomes specified in the project management plan that are achieved through the carrying out the work of the project.

They include products, results, or services – or a combination of these.

Reflect

Take a moment to think about a project you've worked on or know about.

Can you name some outputs – products, results, or services – that resulted from the integrated management of the project?

Enter your thoughts in the field provided, and select the Next Page button to continue.

Write down your response or enter it in a text file in your word-processor application (or in a text editor such as Notepad) and save it to your hard drive for later viewing.

For example, a project aims to develop a version control software tool for managing blueprint versions and sensitive design documentation at an engineering company.

A deliverable of this project is the alpha version of the software, which is tested by an independent test team.

As the project progresses, beta versions are developed. These are tested by a group of users at the client's engineering firm. Eventually, the project will produce the deliverable of the final version of the software. And the software documentation is another deliverable.

Work performance data is an output of the activities the project manager performs to keep track of how the project is progressing.

Graphic

Work performance data may be

This information is collected to determine project performance in terms of factors like costs, the status of project deliverables, and scheduling.

For example, a project manager collects information on the status of each version of the software as it's developed so he knows the attributes and can gauge when the final version will be released. He also collects information on how the project is meeting the planned schedule, and determines the running costs for the project.

Graphic

For example, running costs may be tallied according to project phases, such as Alpha version, Beta version 1, and Beta version 2.

Question

The City Natural History Museum is executing a project to open a new exhibit showcasing prehistoric marine life.

What are some of the outputs that are produced as part of the Direct and Manage Project Work process for this project?

Options:

  1. Tracking information related to the expected arrival time of each exhibition piece at the museum
  2. The instructional graphical user interfaces that provide interactivity within the exhibit
  3. The status of the construction of the display cases commissioned by the museum
  4. The artwork that will form part of the exhibit
  5. The funding for the exhibit
  6. A list of the pieces to be displayed

Answer

Option 1: This option is correct. Tracking information refers to tracking work performance data, which is an output of the Direct and Manage Project Work process. This information is used during monitoring, to ensure the project is kept on schedule.

Option 2: This is a correct option. The graphical user interfaces that will form part of the exhibit are one of the project's deliverables. Deliverables are outputs of the Direct and Manage Project Work process.

Option 3: This is a correct option. Information relating to the completion status of the display cases the museum has ordered is an example of work performance data. This information is one of the outputs of the Direct and Manage Project Work process.

Option 4: This option is correct. Deliverables are outputs of the Direct and Manage Project Work process. The artwork to be displayed as part of the exhibit is a deliverable of the project.

Option 5: This is an incorrect option. The funding for the exhibit is a project resource, not an output of carrying out the project work. The project requires funding to produce outputs.

Option 6: This option is incorrect because a list of the pieces to be displayed in the exhibit would be an output of the Planning processes. It is not an output of the Direct and Manage Project Work process.

Correct answer(s):

1. Tracking information related to the expected arrival time of each exhibition piece at the museum
2. The instructional graphical user interfaces that provide interactivity within the exhibit
3. The status of the construction of the display cases commissioned by the museum
4. The artwork that will form part of the exhibit

Change requests are issued during the execution of a project to ensure that project goals are met. These changes may expand or reduce the project's scope. They may also modify policies or procedures, modify the budget, or adjust the schedule. Change requests are created by members of the project team who notice issues while performing the work. The requests are then reviewed by the project manager and dealt with during the Perform Integrated Change Control process.

For example, in the case of the project developing version control software, all issues discovered during testing are recorded.

Graphic

For example, during version 1.0 testing, the testing officer records the errors that occur when auditing is performed.

These form the basis of change requests that are executed when the next version of the software is developed. Change requests expand the scope of the project as the need for further versions of the software is identified.

Graphic

For example, a change request lists the fixes that should be made in version 1.2.

The project manager adjusts the project budget and schedule to include the increased research and development time and resources needed to produce further versions.

Some change requests involve corrective actions, while others involve preventive actions. Others are generated to update project documentation.

Select each type of change request for further information.

Corrective
Corrective change requests aim to bring project performance in line with the project management plan. They may also address defects, discovered during quality inspections, that need to be repaired.
Preventive
Preventive change requests reduce the occurrence of negative outcomes that may result because of identified risks.
Update
Change requests may involve updating formal project documentation, such as project plans and standards, so they are kept current and reflect any changes or modifications made.

For example, when the alpha and beta testers come across new bugs in the case of the version software, they inform the project manager, who then issues a change request to correct the issue.

During development, one bug keeps recurring, or is fixed in one version of the software but then reappears in the next version. The manager issues a change request to assign two team members to work exclusively on this issue to prevent it from occurring again and causing setbacks.

The project manager then updates formal project documentation, like the quality management plan, to formally record the additional work that must be carried out to correct the quality issues that have been identified.

Updates are added to the project management plan throughout the life of a project.

Graphic

Figure 3-1 of the PMBOK® Guide - Fifth Edition shows that the enter phase/start project leads to the Initiating processes. There is a cyclical relationship between the Initiating, Planning, Executing, and Closing processes. The Monitoring and Controlling processes unite this cyclical relationship. After the Closing processes, the exit phase/end project occurs.

So project management plan updates are an output of many of the project management processes, including the Direct and Manage Project Work process.

For example, the project manager's decision to assign two team members to work on the recurring bug issue resulted in the need for a project management plan update relating to human resources for the project.

Graphic

For example, the additional team members added and assigned to work on error number 467 were Stuart Anderson and Rebecca Franks.

Project documents updates result from approved change requests. As changes are approved, documents must be updated to reflect these.

These documents may include requirements documentation, project logs – such as logs recording issues and lessons learned - and the stakeholder register.

Question

The City Natural History Museum's project to open an exhibit on prehistoric marine life has progressed and further outputs have been produced.

What are examples of other outputs from the Direct and Manage Project Work process for this project?

Options:

  1. A proposal to alter the project's scope because some pieces have been withdrawn from the exhibit
  2. A change to the project management plan after additional staff are hired to prepare the exhibition room in time for the opening launch
  3. Changes to the list of benefactors for the exhibition, because the museum receives a major donation
  4. A document detailing the dimensions of the exhibition room
  5. Procedures for tracking each project activity

Answer

Option 1: This is a correct option. Change requests, like a proposal to alter the scope of the project, are outputs of the Direct and Manage Project Work process. They result from what occurs as project work is carried out.

Option 2: This option is correct because updates to the project management plan are an output of the Direct and Manage Project Work process.

Option 3: This is a correct option. When major donations toward the project are made, the stakeholder register is updated to include these new stakeholders. This is an example of a project document update, which is an output of the Direct and Manage Project Work process.

Option 4: This is an incorrect option. The dimensions of the exhibition room are an example of an enterprise environmental factor for the project. This is an input rather than an output of the Direct and Manage Project Work process.

Option 5: This is an incorrect option. Procedures for tracking activities are an example of an organizational process asset. This is an input rather than an output for the Direct and Manage Project Work process.

Correct answer(s):

1. A proposal to alter the project's scope because some pieces have been withdrawn from the exhibit
2. A change to the project management plan after additional staff are hired to prepare the exhibition room in time for the opening launch
3. Changes to the list of benefactors for the exhibition, because the museum receives a major donation

2. Summary

As a project is executed, it creates outputs, which in turn are used in other project management processes. The outputs generated during the Direct and Manage Project Work process are deliverables, work performance data, change requests, project management plan updates, and project documents updates.

Supplement

Selecting the link title opens the resource in a new browser window.

Follow-on Activity

Access the follow-on activity Directing and Managing Your Own Project to determine what types of outputs your project produces.

Back to top

The Basics of Monitoring and Controlling

Learning Objectives

After completing this topic, you should be able to

1. Monitoring and controlling activities

A project can be overwhelming, no matter what size. Now imagine you let that project carry on its own course without any supervision. The result would be chaos, and a project that ends up achieving very little or something other than what it set out to do. To avoid this, you need to ensure there are adequate supervisory measures in place.

Within the ten Knowledge Areas, Project Integration Management is concerned with identifying and defining various activities and processes within a project, and then bringing them together and coordinating them.

Graphic

An excerpt of Table 3-1 of the PMBOK® Guide - Fifth Edition shows the Monitoring and Controlling processes of the Project Integration Management Knowledge Areas are Monitor and Control Project Work and Perform Integrated Change Control.

In the Monitoring and Controlling Process Group, it's the Monitor and Control Project Work process that interacts with this Knowledge Area.

Reflect

What do you think is the objective of the Monitor and Control Project Work process?

Enter your thoughts in the text box and then select the Compare button to learn more about the aim of this process.

Write down your response or enter it in a text file in your word-processor application (or in a text editor such as Notepad) and save it to your hard drive for later viewing and for comparison with the alternate opinion that follows.

Objectives of the Monitor and Control Project Work process

The Monitor and Control Project Work process aims to track, review, and regulate the progress of a project. This makes potential problems or setbacks easier to identify, and ensures a project stays on track to meet its objectives.

The Monitor and Control Project Work process is not made up of a single type of action. Monitoring and controlling are two distinct activities.

Monitoring involves gathering information about the project's performance. This helps you detect trends by identifying any deviations from, or risks to, the project plan. Then you can take preventive or corrective action if needed.

There are several key monitoring activities you perform in a project:

A project phase to build a prototype of a new gaming device has started. The previous version of this device was a huge success, and a lot of media hype surrounds the new version and its proposed release date. The project manager has the difficult task of making sure that this phase of the project is carried out according to schedule, so fans won't be disappointed.

An important monitoring activity for this project is reviewing progress reports from the gaming technicians.

Adding up product defects is another important activity. The project manager analyzes the reports, and notices some technicians are experiencing problems with the new touch-screen technology that the device uses. The manager makes a note of these product defects for urgent attention.

Some changes are implemented to address the problems with the touch-screen technology. The project manager is assessing the success of the implemented changes by checking progress reports and keeping track of developments.

Select two other examples of monitoring activities that will occur during the project.

Comparing actual with planned results
The project manager checks the progress reports from the technicians against the project schedule. So he compares the technicians' actual progress against the planned progress.

Calculating costs, dates, and other estimates
The project manager regularly calculates and recalculates project costs and completion dates for each phase of work. Because the device must be released on time, he knows it's vital to stick to the planned schedule. So he may factor in higher costs if it means the work will be done on time.

Controlling activities in the Monitor and Control Project Work process involve taking action to correct problems or deviations you discover through monitoring activities.

The following are key controlling activities:

In the gaming device project, the project manager might prepare change requests after processing requests from technicians for new or better software.

He could take corrective action to address the issue with the device's touch screen by arranging for specialists to work on the problem, so it will be resolved as soon as possible.

The schedule may be affected by the delay caused by specialists examining the touch-screen problem. So the project manager will have to re-examine and possibly adjust the schedule baseline for this phase of the project.

Together, the monitoring and controlling activities ensure you keep adequate control over a project, and that it stays headed in the right direction.

Graphic

An excerpt of Table 3-1 of the PMBOK® Guide - Fifth Edition shows all the processes in the Monitoring and Controlling Process Group. They include Monitor and Control Project Work, Perform Integrated Change Control, which belong to Project Integration Management, Validate Scope and Control Scope which belong to Project Scope Management, Control Schedule which belongs to Project Time Management, Control Costs which belongs to Project Cost Management, Control Quality which belongs to Project Quality Management, Manage Communications which belongs to Project Communication Management, Control Risks which belongs to Project Risk Management, Control Procurements which belongs to Project Procurement Management, and Control Stakeholder Engagement which belongs to Project Stakeholder Management.

Question Set

You are managing a project to update the accounting software for a large financial organization.

Question 1 of 2

Question

Match each example to the type of activity it represents. More than one example may match to a type of activity.

Options:

  1. You compare the progress of the upgrade with the planned progress in the project plan
  2. You regularly run software tests and record errors
  3. You analyze the progress reports from the programmers involved in the upgrade
  4. You prepare requests from team members for computer upgrades
  5. You ask programmers to add a security feature to the software that ensures access levels are clearly defined across the organization

Targets:

  1. Monitoring activity
  2. Controlling activity
Answer

The monitoring activities in the Monitoring and Controlling Process Group are concerned with keeping track of the project's progress. This includes comparing actual results with planned results, adding up product defects found during product checks, and reviewing team members' progress reports.

The controlling activities in the Monitoring and Controlling Process Group involve applying necessary changes to a project to keep it on track. This includes preparing change requests and making sure risk response plans are being executed.

Correct answer(s):

Target 1 = Option A, Option B, Option C

Target 2 = Option D, Option E

Question 2 of 2

Question

Match the examples to the types of activities they describe. More than one example matches an activity type.

Options:

  1. You recalculate end-of-project costs to account for some necessary computer upgrades
  2. You've reorganized the programming teams, so you assess whether this change has been beneficial
  3. The work is falling behind schedule so you hire more software consultants
  4. An unexpected glitch in the software has delayed implementation, so you adjust the schedule baseline

Targets:

  1. Monitoring activities
  2. Controlling activities
Answer

The monitoring activities in the Monitoring and Controlling Process Group include calculating end-of-project costs, completion dates, and other estimates, and communicating this information to project stakeholders. They also include assessing if implemented changes have been effective. These activities help you keep track of a project's progress.

The controlling activities in the Monitoring and Controlling Process Group include taking corrective action and adjusting project baselines to account for approved changes. These activities ensure a project does not veer off course.

Correct answer(s):

Target 1 = Option A, Option B

Target 2 = Option C, Option D

2. Project monitoring and control cycle

Given the importance of monitoring and controlling throughout the life of a project, it makes sense to break down the Monitoring and Controlling Project Work process into a manageable cycle.

The monitoring and controlling activities for a project occur as four stages in the monitoring and control cycle. The cycle begins with setting performance standards, which become part of the plan. Once standards have been established, performance can be observed, and compared to those standards. After the actual performance is compared to the planned performance, deviations are easily spotted and can be corrected to bring the actual performance back in line with expectations.

The first stage in the cycle is setting performance standards.

These standards identify the minimum set of expectations for a project.

Reflect

Why do you think setting performance standards is the first stage in the monitoring and control cycle?

Enter your thoughts in the text box and then select the Compare button to learn more.

Write down your response or enter it in a text file in your word-processor application (or in a text editor such as Notepad) and save it to your hard drive for later viewing and for comparison with the alternate opinion that follows.

Usefulness of setting performance standards

Performance standards cover all aspects of the project to ensure it's clear what goals a project team must work toward. They also make it clear exactly what you should be monitoring.

A typical project involves many types of performance standards, including the following:

Performance standards aren't something you develop through monitoring activities. They are derived from project planning.

And the better the planning for a project, the easier it is to monitor and control it once work starts.

Supplement

Selecting the link title opens the resource in a new browser window.

Job Aid

Access the job aid Performance Standards to view a list and brief explanations of the key standards in project control.

The observing performance stage is the one that really kicks off the monitoring activities of the cycle. This is where you gather information, be it formal or informal, about a project's progress. There are many sources for this information, like review meetings, memoranda, reports, letters, and conversations with team members. All of these can provide valuable insight and data.

Graphic

The observing performance stage is the second stage in the cycle. The first stage is setting performance standards. The third and fourth stages are comparing actual with planned performance, and then taking action to correct deviations.

Regular meetings and reports are examples of sources that provide formal information.

For less formal information, a project manager would have to make a little more effort to pay attention to project goings-on. Chats with team members or casual observation of their work habits should not be disregarded. These can bring new information about a project's progress to your attention.

Once you've gathered information about how a project is progressing, the next steps are to compare actual and planned performance and to take action to correct deviations.

Graphic

The first two steps in the cycle were setting performance standards and observing performance.

Select the final two stages in the cycle to learn more about them.

Comparing actual and planned performance
After gathering information, you use it to compare the actual performance of the project to the planned performance mapped out in the project plan. Doing this will tell you about the progress of the project. You'll be able to spot deviations and identify their cause. At this stage, you may also be able to identify what corrective action is needed.
Taking action to correct deviations
Finally, you take action to correct deviations, which constitutes the controlling activities of the cycle. The type of corrective action taken can be as small as making adjustments to the project plan, or it can be reprogramming, reassigning resources, or even changing your project management style. And any action depends on budget and schedule considerations. For example, you may not want to correct a very minor deviation if the change is going to have a major impact on the budget and schedule.

The stages of the cycle make it a lot easier to separate the monitoring and controlling activities that make up the Monitor and Control Project Work process. They also make it clear how these activities work together.

Graphic

The four stages of the cycle are setting performance standards, observing performance, comparing actual with planned performance, and then taking action to correct deviations.

Throughout a project, monitoring activities are necessary to ensure that the project is on track. If corrective action is required, this may involve adjusting project baselines. Adjusting these baselines will create new performance standards – and it's the job of the monitoring activities to ensure these are met. So the cycle continues throughout a project.

Graphic

The four stages of the cycle are setting performance standards, observing performance, comparing actual with planned performance, and then taking action to correct deviations.

Question

Sequence the stages of the project monitoring and control cycle.

Options:

  1. Setting performance standards
  2. Observing performance
  3. Comparing actual and planned performance
  4. Taking action to correct deviations

Answer

Correct answer(s):

Setting performance standards is ranked
Setting performance standards is the first stage of the project monitoring and control cycle. It involves identifying the project standards so it's clear what monitoring activities must track and measure performance against.
Observing performance is ranked
Observing performance is the second stage of the project monitoring and control cycle. This stage entails gathering information in order to find out how a project is progressing.
Comparing actual and planned performance is ranked
Comparing actual and planned performance is the third stage in the project monitoring and control cycle. It enables you to determine if there are any deviations from the plan.
Taking action to correct deviations is ranked
Taking action to correct deviations is the fourth stage of the project monitoring and control cycle. This stage entails taking action to correct any deviations from the project plan.

3. Summary

You use the Monitor and Control Project Work process to keep track of a project's progress and take corrective measures when necessary. Monitoring means you compare actual and planned results, add up product defects, review progress reports, calculate performance forecasts, and assess whether implemented changes have been effective. You control activities by preparing change requests and adjusting baselines as necessary.

The four stages of the Monitor and Control Project Work process are setting performance standards, observing performance, comparing actual and planned performance, and taking action to correct deviations from the plan.

Back to top

Controlling Project Work Performance

Learning Objectives

After completing this topic, you should be able to

1. Monitoring and controlling inputs

If you don't know where you are, you can't tell if you're headed in the right direction. This saying holds true for projects too. It's important to know where your project is at all times, so that if it goes off course you can get it back on track before it goes too far astray in the wrong direction. This is what monitoring and controlling project work is all about.

To monitor and control a project, you need to be able to answer three questions:

There are seven inputs you need for the Monitor and Control Project Work process. These include the project management plan, schedule forecasts, cost forecasts, validated changes, work performance information, enterprise environmental factors, and organizational process assets. Together, the inputs tell you how a project is performing.

The project management plan is a blueprint for how the project will be carried out, monitored and controlled, and finally closed.

Two of the other monitoring and controlling processes provide forecasts that are used as inputs to monitor and control project work: Control Schedule and Control Costs. The cost and schedule forecasts allow you to determine if current project performance is acceptable, or if you need to issue change requests.

During the execution of the change control process, change requests are gathered, reviewed, and may be approved. Any that are approved are validated during the Control Quality process. Validated changes come to the Monitor and Control Project Work process as inputs.

Work performance information is another input to the Monitor and Control Project Work process. This information comes from members of your project team and others within the organization who prepare and submit performance reports, forecasts, and status updates.

In particular, work performance information includes information about several aspects:

Enterprise environmental factors are external or internal factors that can impact a project. Some key factors are government and industry standards and stakeholder risk tolerances.

Project management information systems are another key factor. They are better described as automated tool suites. In other words, systems or tools that perform functions or calculations automatically.

Enterprise environmental factors often place constraints on project work, so they influence the criteria against which the project is monitored and controlled.

Finally, organizational process assets include processes used by the organization itself that can have an impact on the project, as well as historical information and lessons learned from other projects.

You use organizational process assets to define the way that change requests are submitted, approved, and applied. The information from completed projects can also be used to develop estimations and define procedures on current projects.

Key organizational process assets to keep in mind are financial control procedures, such as time reporting, accounting codes, and expenditure reviews. Standard contract provisions are also key assets.

The Foreign Exchange Department of a bank is being upgraded to make it more efficient and pleasant for customers to use.

To determine how the project is progressing in terms of costs, the project manager uses several inputs.

Select each input for an example of how it's used.

Project management plan
The project manager consults the project management plan and uses information from the project's budget to assess where the project should be heading in terms of costs.
Work performance information
She examines a work performance report that details current status and upcoming activities. These will give her an idea of what costs to expect in the coming weeks.
Organizational process assets
The bank has a cost reporting procedure, an organizational process asset that provides the project manager with staff costing reports. She can use these to examine how staff are billing the various project expenses.
Enterprise environmental factors
The forecasting program that the project manager uses is an example of an enterprise environmental factor.
Cost forecasts
She looks at the current estimates to complete projections. If she compares those forecasts to the baselined budget and what it should be at completion, she can tell if the costs will be within the tolerable range.
Validated changes
The project manager consults her list of validated changes and sees that a request to amend the budget was validated two weeks ago. She monitors the change to ensure that it has been properly implemented.

Question

You're managing a project to create and market a line of fruit juices designed to appeal to children.

What are examples of inputs you will use to monitor and control this project?

Options:

  1. The project budget and the schedule detailing the deadline for the completion of the taste test sample
  2. An inventory list of the equipment in the production factory
  3. Time-reporting procedures for keeping track of working hours at the production factory
  4. The original version of a budget that was not included in the final project plan
  5. Software used by the project manager to track the costs of juice ingredients and packaging materials
  6. A report detailing the current status and scheduled activities of the television advertising team

Answer

Option 1: This is a correct option. The planned budget and schedule are examples of baselines contained in the project management plan. These are inputs to the Monitor and Control Project Work process because they're what you measure actual costs and time against.

Option 2: This option is incorrect. An inventory list doesn't provide any information you can use to measure or control project performance.

Option 3: This option is correct. A time reporting process is an example of an organizational process asset. This is an input to the Monitor and Control Project Work process because it is important to understand the processes and procedures for how work is supposed to be carried out.

Option 4: This option is incorrect. The approved budget in the plan is an important input. You monitor actual costs against this. However, using outdated information as a baseline for monitoring costs could be disastrous.

Option 5: This is a correct option. Software that tracks costs would be part of a project management information system, which is an example of an enterprise environmental factor. As an input to the Monitor and Control Project Work process, it would allow you to monitor the project’s cost performance.

Option 6: This option is correct. A report on the current status of the project is an example of a work performance information, which is an input to the Monitor and Control Project Work process. It helps you determine what progress has been made.

Correct answer(s):

1. The project budget and the schedule detailing the deadline for the completion of the taste test sample
3. Time-reporting procedures for keeping track of working hours at the production factory
5. Software used by the project manager to track the costs of juice ingredients and packaging materials
6. A report detailing the current status and scheduled activities of the television advertising team

2. Types of performance

Once you've gathered the inputs that go into the Monitor and Control Project Work process, the next step is to analyze project performance.

Reflect

How do you think you analyze project performance?

Enter your thoughts in the text box and then select the Compare button to learn more about managing a project's performance.

Write down your response or enter it in a text file in your word-processor application (or in a text editor such as Notepad) and save it to your hard drive for later viewing and for comparison with the alternate opinion that follows.

A project performance analysis technique

Analyzing project performance involves comparing planned against actual performance. The baselines in the project management plan provide data for the planned performance. You determine actual performance from information you gather as work proceeds – for example, from work performance reports. Expert judgment will tell you where deviations from the plan are occurring and where these are significant.

The way you measure performance is through a simple subtraction of planned performance minus actual performance. You can use many formulas and applications to calculate the deviations.

First, however, you have to know what types of performance you want to measure. These could relate to a project's scope, time, cost, or quality.

Select each type of performance to find out what it is you would measure.

Scope
When measuring scope performance, you inspect deliverables or their components to assess whether they meet the scope baseline. The process that governs this is the Control Scope process, which is part of Project Scope Management.
Time
You measure time performance by examining the actual schedule to determine if the work is being carried out and completed as planned. You do this as part of the Control Schedule process in the Project Time Management Knowledge Area.
Cost
You measure cost performance by comparing actual costs to those in the cost baseline. This is part of the Control Costs process in the Project Cost Management Knowledge Area.
Quality
You measure quality performance by totaling any defects in the product or service you're creating and by comparing actual quality to the requirements documentation and acceptance criteria. This is part of the Control Quality process in the Project Quality Management Knowledge Area.

Once you've used expert judgment to measure performance in all the key areas, you'll be able to identify where corrective action is needed.

Question

Which are the types of performance that are measured in the Monitor and Control Project Work process?

Options:

  1. Cost
  2. Scope
  3. Expert judgment
  4. Schedule
  5. Baseline
  6. Quality

Answer

Option 1: This option is correct. You measure cost performance to monitor and control adherence to the project's budget.

Option 2: This option is correct. Scope performance will tell you about the acceptability of work results. This is governed by the Control Scope process.

Option 3: This is an incorrect option. Expert judgment is the technique you use to monitor and control performance. It is not a type of performance.

Option 4: This is a correct option. It's important to measure schedule performance to make sure project tasks and activities are done in time.

Option 5: This option is incorrect. Project baselines are important for collecting planned performance data for the Monitor and Control Project Work process, but they are not a type of performance.

Option 6: This option is correct. It's important to measure quality performance as part of monitoring and controlling a project. This lets you determine if the project is on track to meet quality requirements.

Correct answer(s):

1. Cost
2. Scope
4. Schedule
6. Quality

3. Using expert judgment

Once you've measured a project's performance, what do you do if actual performance isn't on track?

As with measuring performance, this takes expert judgment, one of the tools and techniques of the Monitor and Control Project Work process.

You and your project team need to assess if a deviation from plan is significant.

If a deviation is a threat to the success of a project, the next step is to determine what action is required to correct it. However, remember that a project can handle a certain amount of variance. You should decide on that threshold early on.

Graphic

Project variance may be depicted in a graph that has one line for baseline performance and another for actual performance.

If a deviation is significant, you use one of three types of action to bring performance back in line. These are corrective action, preventive action, or defect repair.

Select each type of project control activity to find out more.

Corrective action
Corrective action is used when you need to repair a deviation that has already occurred or to stop it from recurring in the future. For example, deviations found during a quality review, or change requests from customers, require corrective action.
Preventive action
Preventive action is used to stop a potential deviation from occurring. For example, if you know that some team members are resigning, there is a risk that the project will fall behind schedule. This requires preventive action.
Defect repair
Defect repair is the action of correcting product defects found during the Perform Quality Assurance and Perform Quality Control processes. The objective is to bring the product or service back in line with specifications and requirements. Examples of defects that require repair are a machine that is not working properly due to incorrect calibration, bugs in software, or spelling mistakes in a document.

Question

Match each type of project control activity to the circumstance in which it's used.

Options:

  1. Corrective action
  2. Preventive action
  3. Defect repair

Targets:

  1. Fixing a deviation that has already occurred
  2. Stopping a deviation from occurring
  3. Fixing problems in a product to bring it in line with specifications

Answer

Corrective action is used to fix a deviation that has already occurred or to prevent it from happening again in future.

Preventive action is used to stop a foreseeable deviation or risk from occurring.

Defect repair is used to fix product defects found during the Perform Quality Assurance and Perform Quality Control processes to bring a product back in line with requirements.

Correct answer(s):

Target 1 = Option A

Target 2 = Option B

Target 3 = Option C

Once you've identified the type of project control activity needed, you need to determine how to apply it to correct the deviation.

Supplement

Selecting the link title opens the resource in a new browser window.

Job Aid

Use the job aid Assessing and Controlling Performance as you monitor and control performance on your projects.

For example, a corrective action to address cost overruns might be to add more money to the budget. Or in the case of a schedule deviation, it could mean adjusting remaining activities to make up for time lost earlier on.

Graphic

For example, a task that was originally schedule to be completed on the 24th day of the month may be moved up to complete on the 11th.

You may have spotted something that requires preventive action. For example, if you know that a major supplier for the project is about to be liquidated, you can prevent delays by identifying an alternate supplier in good time.

Other examples of preventive actions include the following:

An example of a defect repair could involve recalibrating a machine, or replacing parts that are too big or small for it. Bugs in software could be fixed by adjusting the code. And text containing mistakes in a document could be deleted, rewritten, or edited.

Question

Match each type of project control action to an example.

Options:

  1. Corrective action
  2. Preventive action
  3. Defect repair

Targets:

  1. Allocating more time to a task that is falling behind schedule
  2. Training employees to use a new software system
  3. Fixing a color error in a graphic

Answer

Allocating more resources to a task that is already falling behind schedule is an example of corrective action. This fixes the problem and prevents it from recurring.

Training employees is an example of preventive action. This will help prevent employees from making errors when using the system, which could cost time and money to fix.

Fixing an error in a graphic is an example of defect repair. This will bring the product back into line with requirements or specifications.

Correct answer(s):

Target 1 = Option A

Target 2 = Option B

Target 3 = Option C

Recall the project to renovate the foreign exchange department of a bank. The project manager found that the costs of the project were running over by 15% and that this trend would continue unless something was done about it.

The project manager discovers that the key cause of the deviation is that team members were charging some of the expenses to the project, rather than to the bank's general operating account.

The problem lies in the accounting program that's used to monitor expenses. So the most appropriate immediate action for the project manager to take is corrective action to fix the problem with the program.

She adjusts the program so the codes that team members enter are billed to the correct account.

In this case, the project manager can also take preventive action to stop further deviations of this kind from occurring. She adjusts the document that sets out the billing procedure to ensure it's clear and that the accounting codes are up to date. She also briefs team members about the changes.

Question

You're managing a project to expand the number of a bank's automatic teller machines, or ATMs, across a city. The project is falling behind schedule.

Which is an example of an appropriate corrective action to get the schedule back in line?

Options:

  1. Fix errors in the interface used by the ATMs to avoid having to make later adjustments
  2. Shorten the duration of some of the later tasks, such as collating expense reports, so that deadlines can be met
  3. Take no action because the factors causing the delay are out of your control
  4. Get expert advice from team members about how to speed up activities on future projects

Answer

Option 1: This option is incorrect. Fixing defective ATMs would be an example of defect repair. This won't help bring the project back in line with the schedule though.

Option 2: This is the correct option. Shortening the duration of other tasks is an example of corrective action. This will fix the existing problem by allowing more time for the current tasks.

Option 3: This option is incorrect. As project manager, you have the authority to request changes to the way project work is done. This is how you apply corrective action that will bring the project back in line with the schedule.

Option 4: This is an incorrect option. Getting advice on how to speed up activities on future projects is an example of a preventive action. This won't fix the current deviation – it will only help prevent future deviations.

Correct answer(s):

2. Shorten the duration of some of the later tasks, such as collating expense reports, so that deadlines can be met

4. Other tools and techniques

Expert judgment is one tool and technique of the Monitor and Control Project Work process. The others are analytical techniques, project management information system, and meetings.

Select each tool and technique to find out more.

Analytical techniques
Analytical techniques are used to determine the health of a project, factors that explain current performance, and determine where its performance is headed. Examples of techniques include root cause analysis and trend analysis.

Project management information system
If you use project management software to automate data gathering and analysis, you will use the application during the Monitor and Control Project Work process. This type of tool gives you immediate access to resource information, databases, project records, and financials.

Meetings
In conjunction with expert judgment, meetings are used to discuss project performance with team members and other stakeholders. Meetings may be in-person or virtual, formal or informal.

Question

Besides expert judgment, what are the other tools and technique used during the Monitor and Control Project Work process?

Options:

  1. Meetings
  2. Analytical techniques
  3. Project management information system
  4. Facilitation techniques
  5. Project management plan

Answer

Option 1: That is correct. Meetings are a common way to get project team members and stakeholders together to discuss the project and make decisions during the Monitor and Control Project Work process.

Option 2: That is correct. Analytical techniques are an important way to determine the health of a project during the Monitor and Control Project Work process.

Option 3: That is correct. A project management information system will make life much easier during the Monitor and Control Project Work process as you gather and analyze complex data and information from many sources.

Option 4: That is an incorrect option. Facilitation techniques are used during the Develop Project Management Plan process.

Option 5: That is an incorrect option. The project management plan is an input to the Monitor and Control Project Work process, not a tool or technique.

Correct answer(s):

1. Meetings
2. Analytical techniques
3. Project management information system

5. Summary

The Monitor and Control Project Work process uses seven inputs – the project management plan, schedule forecasts, cost forecasts, validated changes, work performance information, enterprise environmental factors, and organizational process assets.

Once you've gathered the inputs, you use expert judgment to measure project performance. This involves comparing actual to planned performance, and identifying significant deviations. You also use analytical techniques, a project management information system, and meetings to monitor and control project work.

Back to top

Updating Project Baselines

Learning Objectives

After completing this topic, you should be able to

1. Monitoring and controlling outputs

The results, or outputs, of the Monitor and Control Project Work process helps ensure that your project stays on track and meets objectives throughout its life cycle. This process also affects other areas of the project.

Graphic

A generic project life cycle is represented by Figure 2-8 of the PMBOK Guide - Fifth Edition. It contains four phases – starting the project, organizing and preparing, carrying out the work, and closing the project. Costs and staffing levels rise through the fist three phases, then decrease as the project comes to a close. As work is monitored and controlled throughout the life cycle, it helps meet project objectives.

While you monitor and control project work, you often have to suggest changes to get things back on track or prevent future problems. If these changes are approved, they can impact a project's baselines. So updates to the project management plan, including the scope, schedule and cost baselines, are one output of the process.

Besides updates to the overall project management plan and subsidiary project baselines, there are three other outputs of the Monitor and Control Project Work process:

Although these three outputs won't be covered in detail in this topic, you should still be aware of what they are and the impact they have on a project.

Select each output for more information about it.

Change requests
You issue change requests to recommend corrective or preventive action, or to repair defects. For instance, you might issue a change request to incorporate a feature a client requests in a software program. If the request is approved, work to add the feature can go ahead.
Work performance reports
Work performance reports are the result of processing the raw work performance data and placing the resulting information in a format that stakeholders can easily understand. Reports are used to raise awareness, generate discussions, and make decisions.
Project documents updates
Examples of project documents are work instructions, the project risk register, and the issue log. As changes are made to the project, all documents containing information impacted by the changes must be updated.

Question

What are the outputs of the Monitor and Control Project Work process?

Options:

  1. Change requests
  2. Project documents updates
  3. Work performance information
  4. Deliverables
  5. Updates to the project management plan

Answer

Option 1: This option is correct. If approved, change requests usually result in updates to numerous project documents, including the project management plan.

Option 2: This is a correct option. Project documents updates are performed during the Monitor and Control Project Work process when issues come up, change requests are approved, or work performance information is gathered.

Option 3: This is an incorrect option. Work performance information is an input to the Monitor and Control Project Work process. The output of the Monitor and Control Project Work process is work performance reports.

Option 4: This option is incorrect. Deliverables are an output of the Direct and Manage Project Work process.

Option 5: This option is correct. When project baselines and subsidiary documents are altered due to change requests being approved, this can generate updates to the project management plan.

Correct answer(s):

1. Change requests
2. Project documents updates
5. Updates to the project management plan

2. Controlling project work

Reflect

The remainder of the topic will look more closely at project management plan updates.

What might happen if baselines are not updated as a result of change control activities?

Enter your thoughts in the text box provided and then select the Compare button.

Write down your response or enter it in a text file in your word-processor application (or in a text editor such as Notepad) and save it to your hard drive for later viewing and for comparison with the alternate opinion that follows.

What happens when baselines aren't updated

Imagine a project where the scope has increased to include extra work but the schedule baseline hasn't been updated. With extra work added, it probably won't be realistic to try to meet the original delivery date. But without updating the baseline, reporting can't be done accurately, so the results of any subsequent monitoring and controlling will be skewed.

Margaret is managing a project that's part of a larger program to develop and market a new type of ammonia-free fertilizer. This new fertilizer will increase corn and wheat crop yields, while minimizing health risks to humans and animals. During the course of the project, Margaret has to make several updates to baselines.

The scope of the project includes developing two separate designs and prototype samples – one tailored for corn and the other for wheat.

The project's highest constraint is quality. If government-regulated quality standards aren't adhered to, the products won't be approved.

Based on what she finds through the Monitor and Control Project Work process, Margaret needs to correct mistakes, prevent negative outcomes, or repair defects to the products throughout the project.

3. Corrective and preventive action

As the project to develop the ammonia-free fertilizer begins, one of the machines in the lab breaks down. Tom, one of the technicians, has brought this to Margaret's attention.

There aren't any other labs in the area that use the same equipment, so Tom calls the manufacturer, who informs him that they'll need to fly in a repair technician from another city.

He finds out the technician is available only the following week and that the repairs could take up to two days to complete.

When Tom tells Margaret about the situation, she says she'll make some changes to the schedule baseline to account for the delay. Although the equipment is under warranty, Margaret has to charge the project for the technician's transport and accommodation. So she adds $1,000 to the budget.

Question

In this case, hiring someone to repair the piece of broken equipment is an example of corrective action. How do you think this could impact the way the project would be monitored and controlled?

Options:

  1. Margaret needs to adjust the baselines against which future work is monitored and controlled
  2. The project will now run over budget, so Margaret will have to cut costs somewhere else
  3. The project can't complete on time, since the schedule can't absorb the repair's delay
  4. Equipment must be inspected weekly for signs of wear and tear to avoid another breakdown

Answer

Option 1: This option is correct. A change to a project often requires updates to one or more project baselines.

Option 2: This option is incorrect. Because the lab equipment had to be repaired, the schedule is delayed by three days, and the cost of the technician's transport and accommodation has to be billed to the project. To account for this, the schedule baseline and the cost baseline are updated.

Option 3: This option is incorrect. Because the lab equipment had to be repaired, the schedule is delayed by three days, and the cost of the technician's transport and accommodation has to be billed to the project. To account for this, the schedule baseline and the cost baseline are updated.

Option 4: This option is incorrect. Because the lab equipment had to be repaired, the schedule is delayed by three days, and the cost of the technician's transport and accommodation has to be billed to the project. To account for this, the schedule baseline and the cost baseline are updated.

Correct answer(s):

1. Margaret needs to adjust the baselines against which future work is monitored and controlled

While reviewing a performance report, Margaret notices that one of the chemist's titration test results shows that the chemical composition of the test sample is all wrong. If this is not rectified, the product won't meet quality standards.

Margaret discusses the problem with the chemist, Andrew. He wasn't aware of the inaccuracy until she brought it up. Now he'll have to redo the work before they can send the samples off for final testing. It will take three days to fix.

Redoing the work causes a delay. But it will save the project a lot of trouble that could result from allowing the defective sample to be used.

So Margaret adjusts the schedule baseline to account for a delay of three days. Then she uses the company's forecasting tool to establish revised end dates and total costs for the project.

Reflect

What principle do you think Margaret has in mind when she revises the schedule and cost baselines after Andrew agreed to redo his work?

Enter your thoughts in the text box and then select the Compare button to learn more about updating baselines when monitoring and controlling project work.

Write down your response or enter it in a text file in your word-processor application (or in a text editor such as Notepad) and save it to your hard drive for later viewing and for comparison with the alternate opinion that follows.

Updating baselines to reflect changes

Margaret knows that there are other members of the team who rely on her to give them the most up-to-date and accurate information on the project. She makes sure to adjust the baselines to reflect the changes so that future efforts to monitor and control project work are not skewed.

4. Defect repair and scope reduction

Because the project team is developing a fertilizer, a product that will affect food quality, there are strict guidelines on how to use clinical research studies for the project.

Graphic

Margaret consults guidelines for the use of clinical studies.

For example, the studies can't be older than five years and they must list all adverse reactions for each ingredient.

Jennifer, the quality reviewer, has checked the project design and found that some of the quality criteria haven't been met. At least three of the clinical studies that were referenced weren't conducted recently enough to be valid. She brings this to Margaret's attention.

Question

What kind of adjustments do you think Margaret needs to make after discovering the clinical trials were not conducted properly?

Options:

  1. Requesting an improvement to the way that clinical studies are sourced by the development team
  2. Modifying the schedule baseline to account for the delay caused by the rework
  3. Assessing the amount of time it will take to rework the clinical studies
  4. Given that it's too late to change what has happened on this project, Margaret should make sure the same thing doesn't happen on the next project
  5. Margaret should request an adjustment to the quality criteria, so that the studies the team has used will be considered acceptable

Answer

Option 1: This a correct option. As a means of defect repair, Margaret should issue a change request that outlines the way that the team should source clinical studies that are appropriate for use on this project.

Option 2: This option is correct. The baseline must be updated so that future monitoring and controlling of the project will be done according to accurate measures.

Option 3: This is a correct option. It is important that Margaret has a sense of how long it will take to redo the work, so that she can use this information to adjust the schedule baseline.

Option 4: This is not a correct option. This project cannot continue to the next phase in development if the quality criteria haven't been met. So Margaret should issue a change request, asking the development team to source more appropriate clinical trials.

Option 5: This is an incorrect option. The highest constraint on this project is quality, meaning that the quality criteria are non-negotiable. Instead of requesting that the quality requirements be relaxed, Margaret should request a change that ensures the development team meets the criteria that already exist.

Correct answer(s):

1. Requesting an improvement to the way that clinical studies are sourced by the development team
2. Modifying the schedule baseline to account for the delay caused by the rework
3. Assessing the amount of time it will take to rework the clinical studies

After Jennifer speaks to the development team, she calculates how long the rework would take, and Margaret adjusts the schedule accordingly. Margaret suspects that the problem could have occurred because the requirements weren't explained clearly enough. So she looks at the quality management plan and makes some adjustments there too. She also asks the team leader to revise the work instructions on how to locate appropriate clinical studies and to e-mail those to the team.

Margaret makes sure her next report to Alex, the program manager, includes all the schedule changes that have been made.

So when he reviews it, he is able to monitor how this project's development fits in with the overall program schedule.

Follow along as Alex and Margaret discuss how the project schedule impacts the program as a whole.

Alex: Margaret, I'm concerned that unless we do something, your project won't be completed in time for the pilot program to test the fertilizers.

Margaret: I agree that there have been a lot of additions to the schedule. What do you suggest we do?

Alex: From my calculations, it looks like we need to pull the completion date in by three weeks. I think the best way to get that done is to reduce the project scope so we focus only on fertilizers for corn.

Margaret: That's a good suggestion. I'll remove all the activities related to producing the wheat fertilizer, and then I'll e-mail you the revised schedule.

Alex: I look forward to the new dates. We'll take it from there if this doesn't resolve the issue.

Alex sends Margaret some market research information showing that there is greater demand for corn than for wheat, given the drive for biofuels.

So Margaret presents this information at a meeting with the project team and she explains that they will narrow the scope of the project to eliminate all activities related to producing the wheat fertilizer.

She forecasts that the scope reduction actually saves 20 days, so she revises the schedule baseline to reflect this, hoping that there won't be too many more unforeseen changes.

Graphic

The schedule baseline she uses is in the form of a Gantt chart.

Question

Think about the fertilizer development project.

Which are true statements about updating project baselines?

Options:

  1. When a change request was approved on the project, this caused project baselines to be adjusted
  2. If Margaret hadn't updated the baselines to reflect changes, future efforts to monitor and control project work would be skewed
  3. Margaret could increase or decrease the baselines according to the project needs and constraints
  4. When a change was made to one baseline, usually other baselines were affected as well
  5. Margaret was wrong to keep adding to the schedule because this led to a change in the project's scope
  6. A project scope baseline should be updated regularly to reflect changes in market conditions

Answer

Option 1: This option is correct. Usually when you change an aspect of the project it will require an adjustment or update to the relevant project documents.

Option 2: This is a correct option. When you make a change to any aspect of the project, that causes deviation from the plan, you need to update the relevant baseline, to bring actual and planned performance back in line.

Option 3: This option is correct. The project manager uses expert judgment to measure what kind of action to take to bring planned project performance back in alignment with actual performance. This could mean either increasing or decreasing a baseline.

Option 4: This is a correct option. Many aspects of a project are dependent on one another, so an adjustment to one aspect typically leads to updates in other areas as well. For instance, when you increase a project's scope, you usually have to increase the time or resources allocated to the project as well.

Option 5: This option is incorrect. Margaret added to the schedule as a means of corrective and preventive action, and to repair a defect. These were necessary steps in controlling the project, which then led to a reduction in scope.

Option 6: This is an incorrect option. Market conditions are an example of an enterprise environmental factor. Changes in these factors don't automatically lead to project baselines being updated. Updates are generated when change requests are approved.

Correct answer(s):

1. When a change request was approved on the project, this caused project baselines to be adjusted
2. If Margaret hadn't updated the baselines to reflect changes, future efforts to monitor and control project work would be skewed
3. Margaret could increase or decrease the baselines according to the project needs and constraints
4. When a change was made to one baseline, usually other baselines were affected as well

5. Key principles

Think about the examples presented so far. Each of them contains principles that apply to updating project baselines.

There are four principles for updating baselines:

Select each principle for more information about how it was represented in the examples from the fertilizer project.

Change requests cause baselines to be adjusted
Each time Margaret had to take corrective or preventive action, or ask for a defect repair, she made a change to one or more of the baselines. For example, when the lab equipment broke down, Margaret had to adjust the schedule to reflect the delay caused by the repairs. She also adjusted the budget to include the cost of transport and accommodation for the technician.

Changes to one baseline affect other baselines
The principle that changes to one baseline affect other baselines was demonstrated when the guidelines for using clinical studies weren't followed. Repairing this defect required updates to the schedule, the quality management plan, and the work instructions for the project.

If baselines aren't adjusted, future monitoring and controlling will be skewed
If baselines are not adjusted to reflect changes, they won't be an accurate means of monitoring and controlling project work. Because Margaret always updated all the relevant project baselines to include changes, the program manager was able to effectively monitor and control the program as a whole.

Project baselines may be increased or decreased
This principle was demonstrated by the way that Margaret and Alex, the program manager, monitored and controlled project and program work. Margaret increased the schedule baseline to account for the delays on the project. Then Alex's change request caused a reduction in project scope and schedule. The decision to increase or decrease the baselines depended on the constraints and needs of the project.

6. Summary

When you monitor and control project work, your aim is to ensure that the project meets its objectives despite unexpected deviations from the plan.

The outputs of this process are change requests, project management plan updates, project documents updates, and work performance reports.

Change requests often cause project baselines to be adjusted. They can result in project baselines being increased or decreased, depending on the constraints and needs of a project. Typically, a change to one baseline affects other baselines as well. When a change is made, you have to adjust the baselines to reflect those changes, or future efforts to monitor and control project work will be skewed.