1. Principles of Integrated Change Control
2. Using the Change Control Process
In an orchestra, many instruments play different notes at the same time. The conductor must pay attention to what each section of the orchestra is doing. For example, when leading the string section, the conductor must consider how its music will affect the woodwinds and brass sections. If the conductor focuses on just one section, the other musicians will not receive the direction they require in order to produce a unified and beautiful effect.
Like the conductor leading the orchestra, a project manager must also lead a project in an orchestrated way. Decisions related to controlling costs may affect time lines, quality, human resources, and many other aspects of the project.
Project issues, decisions, and administrative activities must be looked at from all sides and managed in an integrated way.
A key aspect of bringing everything together within a project is managing project changes effectively. By controlling change and responding carefully to a changing environment, you're better able to ensure successful completion of a project. Then when it's completed, you can follow closing procedures to ensure there are no loose ends. And you can also provide documentation that'll help generate further success in new projects.
Change must be controlled through all the phases of a project, including initiate, plan, implement, and close.
This course outlines the principles you should follow when managing the Perform Integrated Change Control process. It covers what inputs you can use in this process, what activities need to be performed, and what the outcomes of the process are.
The course also explains the Close Project or Phase process, guiding you how to ensure product acceptance, tie up loose ends, and assess the project's success.
After completing this topic, you should be able to
Changes are inevitable during a project. So handling change well is key to every project's success. The Perform Integrated Change Control process can help you deal with change effectively. This process involves reviewing, approving, and managing changes to project deliverables, plans, and processes.
The change review, approve, and manage process is cyclical in nature.
The Perform Integrated Change Control process is triggered when there's a change request generated as an output of project work processes or control processes.
If members of the project team make even small changes without using the process, these could accumulate and badly affect the project scope, budget, and schedule.
Every change, no matter how small, should go through the control process. This avoids scope creep. And it helps ensure only necessary changes are approved and that the project remains within budget and on schedule.
So how can you effectively manage changes? There are several principles of the Perform Integrated Change Control process that you should follow. First, you need to develop a method to identify when changes to the baseline plan occur. Second, you need to address and manage changes promptly. And third you should track and document the impact of the changes.
Select each key principle of the Perform Integrated Change Control process for examples of how it can be implemented.
What are three key principles of the Perform Integrated Change Control process?
Options:
Option 1: This option is correct. Project managers need to develop methods, such as weekly or daily reports, to help them to identify potential and actual changes to the baseline project plan.
Option 2: This is a correct option. Delaying your response to changes may impact on the cost, schedule, and feasibility of making necessary changes.
Option 3: This option is correct. By documenting the impact of changes, you learn more about how changes may affect the project and you develop useful resources for other project managers or projects.
Option 4: This option is incorrect. Documenting the impact of changes may lead to updates of risk management plans. However, not all changes will affect risk management.
Option 5: This option is incorrect. Although a change management team is often useful, not every project needs one.
Correct answer(s):
The fourth principle of the Perform Integrated Change Control process is to review and assess change requests before making a decision to reject or approve them. Reviewing and assessing change requests is one of the main activities of change control.
When reviewing a change request, you need to determine who initiated the request and what type of change it asks for. You also need to understand the factors that have led to the request – these may be customer demands, changes in legislation, technical difficulties, and so on.
You need to assess what impact the change could have on scope, quality, schedule, and cost. Suppose the change you're considering pushes out the scheduled completion date. That means you'll need resources longer than expected and this will cost the customer more.
Finally, you need to decide whether the change should go ahead. To help you do this, you need to ask yourself whether the benefits of making the change increase or decrease the chances of successful project completion while still meeting the project objectives. You should then make a record of your decision.
The final three principles of Perform Integrated Change Control relate to making sure a project sticks to the project management plan when possible. To do this, you should implement only approved changes, adjust the project baselines only when necessary, and coordinate approved changes.
Examples of types of changes that must be coordinated include scope, quality, cost, and schedule.
Select each principle for more information about it.
Selecting the link title opens the resource in a new browser window.
Job Aid
Access the job aid Change Control Principles to review the list of principles that should be followed in the Perform Integrated Change Control process.
It's important to remember that project baselines should be changed only when absolutely necessary. Always look for an alternative solution to managing the change.
For example, a stakeholder might demand a new feature for the product you're developing. On assessment, you find this change is beyond the project's scope.
Because the feature is a major departure from the project scope statement and is not absolutely necessary, the change control board rejects the change request. This protects the project baseline and helps to manage stakeholder demands more effectively.
Which statements correctly describe principles of the Perform Integrated Change Control process?
Options:
Option 1: This option is correct. Each change request should be reviewed in terms of who initiated it and what led to it. The change request should be assessed to determine whether the change it asks for is justified. Then the request can be approved or rejected.
Option 2: This is a correct option. If you implement changes that have not been approved, you're likely to affect the project baselines and may place the project at risk.
Option 3: This option is correct. Changes to project baselines can have an enormous impact on project processes, schedules, quality, and resources. So it's important to consider these kinds of changes carefully before approving them.
Option 4: This is a correct option. Changes to one aspect of a project often have implications for its schedule, budget, and resource requirements. Changes may also impact several processes within the project. These changes should be integrated and coordinated across the project.
Option 5: This is an incorrect option. A complete risk assessment is not needed for a change request you reject. But you should document that the request has been rejected.
Option 6: This option is incorrect. All requests for change should be processed in the same way. Eventually, small changes add up. If they're not managed properly, they could put a project at risk.
Correct answer(s):
So now that you've been introduced to integrated change control, there's another aspect to this that you'll hear a lot about in project management – configuration management. This is an important aspect of integrated change control.
You can think of configuration management as a fancy term for version control. A configuration management system is an all-encompassing system of procedures, software, and policies used to control versions of the product and its components. It also controls all product-related documentation and key project management documents, such as the project management plan and various logs.
So why is configuration management so important?
It prevents version-related errors, such as delivering the wrong version of a product to the customer, testing the wrong version, or losing the correct version by mistakenly over-writing it with an out-of-date one.
Configuration management tools perform similar roles as the Confirm File Replace message on your computer that requires you to confirm that you want to replace an existing file.
The larger a project is, the more complex the processes you follow, and the more people you have working on it. In these cases, mistakes are likely to happen. Using a configuration management system greatly reduces the risk of errors.
A configuration management system retains all of the evolving versions of a product and related documents throughout production.
Do you think such a system has benefits for a project manager?
Options:
There are many times during a project when the version history of a product or document comes in very handy. For example, if an unwanted change creeps in along the way, you can retrace the versions to learn how it happened and who made the change.
Correct answer(s):
Besides ensuring version control, the configuration management system has another important role. It establishes a set of processes and checks for ensuring that only approved changes are made to the product and project documents. This is where the change control system comes into play. It's a subset of the configuration management system.
Configuration management involves three main activities that are directly related to the change control system. These activities involve identifying the characteristics of a product or service, controlling changes to those characteristics, and documenting and auditing these changes to ensure requirements are met.
Select each activity for more information about it.
Consider an example of how normal change control activities correspond to the three configuration management activities. Suppose you're managing a project to develop a new media player. An update to a media format is released and your customers decide they want the new player to be able to handle it.
Because the media player is a configuration item, you first review the product specifications recorded in the quality management plan. This tells you what formats the media player is currently designed to support. Unfortunately, the new format is not on the list.
Next you check the product status log to see what stage of development the product is currently in. You also log the change request, document when a change control board meeting should be held to consider the request, and document what the change may entail.
If the change is rejected, you simply log the rejection in the change control log. If the change is accepted, you need to update the change control log and make changes to the project plan, depending on how the change will impact the project's scope, budget, schedule, and resource requirements.
The change request is approved by the change control board and the media player is adapted to handle the new media format. The media player is tested during the quality control process to ensure that it can play back media correctly using the new format. If the player fails testing, corrective action will be required.
A quality control specialist may use an audit sheet that has two checkboxes: Working and Not working.
A clothing company has initiated a project to develop a new range of sportswear. A key stakeholder submitted a late request, asking for the designs to include reinforced seams on all garments.
Match each example to the configuration management activity to which it applies. More than one example may apply to a management activity.
Options:
Targets:
Reviewing and documenting the specifications for the design is one aspect of the configuration identification activity.
Logging change requests is an aspect of configuration status accounting, which also involves logging the implementation status of approved requests.
Checking the specifications of the changes is an aspect of the configuration verification and auditing activity. This is to ensure the product still meets the specified requirements.
Correct answer(s):
Target 1 = Option A
Target 2 = Option D, Option B
Target 3 = Option C
So a configuration management system includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes to a product. A project's change control system is the mechanism through which this is done.
What is the relationship between an organization's configuration management system and the change control system used on a project?
Options:
The configuration management system is the overall system, of which the change control system is a part. The configuration management system provides the tools needed to control project changes.
Correct answer(s):
The Perform Integrated Change Control process involves reviewing, approving, and managing changes to project deliverables, plans, and processes. This process helps ensure only necessary changes are approved and made, so a project remains within budget and on schedule.
The configuration management system provides tools for implementing the Perform Integrated Change Control process. The change control system documents needed characteristics of a product or service, documents the change control process, and audits results to determine whether all specifications and requirements have been met.
Selecting the link title opens the resource in a new browser window.
Follow-on Activity
Access the follow-on activity Integrating Change Control to find out about your company's configuration management system and how it's used for integrated change control.
After completing this topic, you should be able to
Change is a fact of life. And how you manage and control change during the life of a project will determine that project's success.
The Perform Integrated Change Control process is designed to review change requests and manage approved changes to deliverables, organizational process assets, project documents, and the project plan.
The process of reviewing, approving, and managing change is cyclical in nature.
To use the Perform Integrated Change Control process effectively, you need to be aware of its key inputs, tools and techniques, and outputs.
Figure 4-10 of the PMBOK® Guide - Fifth Edition shows that the inputs to the Perform Integrated Change Control process are the change requests, organizational process assets, project management plan, work performance information, and enterprise environmental factors. These are used in the tools and techniques of the process, which include change control meetings, change control tools, and expert judgment. The outputs are approved change requests, the change log, project management plan updates, and project document updates.
The main inputs to the Perform Integrated Change Control Process are change requests. Changes may include corrective actions, preventive actions, and defect repairs. Most change requests are recommendations or requests generated as the project progresses.
Change requests can come from any of the processes in the Project Integration Management Knowledge Area, such as Direct and Manage Project Work or Monitor and Control Project Work. Change requests may also be generated by any of the control processes, such as Control Scope or Control Costs.
Change requests are then fed into the Perform Integrated Change Control process.
Select the Direct and Manage Project Work box and the Monitor and Control Project Work box for examples of change requests from each process.
Selecting the link title opens the resource in a new browser window.
Job Aid
Access the job aid Change Request Template for guidance on creating a standard change request.
Suppose a delay in receiving components threatens to put a project one month behind schedule. The project manager, the project team, and even the stakeholders can examine the project schedule to see what possible alternatives can be used to bring the project back on track.
Solutions may include using additional team members to carry out the work and changing the order in which some of the work is completed. Certain areas of the project could also be fast tracked to ensure the project is completed on time.
Once a workable solution has been planned a change request is sent to the change control board, which then uses expert judgment to approve or reject the request.
Other inputs into the change control process are organizational process assets, including the configuration management knowledge base, change control procedures, and project files.
Select each organizational process asset for more information on how it influences the change control process.
Betty Park is a project manager for a hospital project. She has a reporting process in place to ensure she's updated with any potential changes that may impact the project. Team members send her daily e-mails about their progress and problems.
For example, Betty has a table with two columns called Group and Status. There is a row for each group in which Betty records status, such as completed, pending, not started, or in progress.
She notices that quality control procedures are taking longer than expected due to the various legal requirements for these checks. Betty shuffles her "To Do" list to make change management a priority and begins reviewing the configuration management knowledge base.
Betty has two items on her To Do list: quality control procedures and change management. She has circled change management to show it is now her top priority.
She checks the knowledge base to determine how similar problems were managed in the past and what lessons were learned.
Betty finds some potential solutions for the delays that are occurring in carrying out quality control procedures. She reviews the project files for the current project to assess the potential impact of these solutions on scope, cost, schedule, and quality.
Once she is clear on what the best possible solutions are, Betty checks the documentation outlining the change control procedures. Using these to guide her, she draws up a change request.
So in responding to problems that arise, Betty uses organizational process assets. These include the knowledge base, project files, and change control procedures. She also follows change control principles by ensuring there is a method for identifying change – daily e-mail reports – and by dealing with change issues promptly.
What are examples of inputs to the Perform Integrated Change Control process?
Options:
Option 1: This is a correct option. Change requests are the main input to the process. The request in this case is an input from the Control Scope process, which is in the Monitoring and Controlling Process Group.
Option 2: This option is correct. This change request is an input from the Direct or Manage Project Execution process or the Monitor and Control Project Work process.
Option 3: This is a correct option. Baselines are part of the configuration management knowledge base, which is an example of an organizational process asset that can be an input to the change control process. Baselines can be used to review and assess the potential impacts of changes.
Option 4: This is a correct option. Change control procedures are inputs to the Perform Integrated Change Control process. They determine how changes must be handled.
Option 5: This is an incorrect option. Updates to project plans can result from the Perform Integrated Change Control process – they're not an input to the process.
Option 6: This option is incorrect. Change control meetings are a tool in the Perform Integrated Change Control process, rather than an input. The change control board assesses and approves or rejects change requests.
Correct answer(s):
There are three remaining inputs to the Perform Integrated Change Control process:
The other inputs include change requests and organizational process assets.
Select each input for an example of how it is used during the Perform Integrated Change Control process.
Change requests and organizational process assets are two examples of inputs to the Perform Integrated Change Control process.
What other examples of inputs can you identify?
Options:
Option 1: This is a correct option. The project management plan contains the dates on which the tasks of a project are planned to complete. The plan becomes an example of an input to the process because this information is compared against the actual completion dates to discover if the project runs as planned, or if the changes need to be applied.
Option 2: This is a correct option. A work performance report tells you about the cost that a project has incurred to date. It is an example of an input to the process because it allows you to compare planned cost to actual cost, and initiate a response if these figures deviate. If the planned cost was set at a third of all venue cost, then this project is running according to budget.
Option 3: This is a correct option. You would use the project management information system for the project to manage a change in cost. Your company's project management information system is an example of an enterprise environmental factor which is an input to the process that manages change.
Option 4: This is an incorrect option. The update to a project's documentation is not an input to the process. Instead, the updated project management plan is an output of the process.
Option 5: This is an incorrect option. Requesting assistance from a colleague who has experience in running a project similar to your own is not an example of an input to the process. Expert judgment is a tool that you use to process the inputs.
Correct answer(s):
There are three tools and techniques used in the Perform Integrated Change Control process – expert judgment, change control meetings, and change control tools.
The project manager uses the expert judgment of the entire project team to make change control decisions. Other stakeholders, such as consultants or the customer, may also provide expertise.
Expert judgment about how to control project change is generally obtained during change control meetings.
There are many manual and automated tools that the project manager may use during the change control process. For example, communication technologies such as e-mail and online collaboration sites are used to manage change requests and communicate decisions made during the meetings.
To understand change control tools and meetings and how expert judgment is used in the change control process, you need to understand the role played by the change control board.
This board reviews change requests and approves or rejects each proposed change. The range of the project manager's responsibility in approving or rejecting minor change requests is clearly set out and must be approved by all key stakeholders.
All change control board decisions are documented and communicated to stakeholders.
The role of the change control board depends on the change control system set up for a project and the level of authority – either high or low – the project manager has been granted. Select each system type for more information.
Members of the change control board can include stakeholders, managers, technical experts, and project team members, as well as others who might not have any connection to the project.
Others may be called in for their expert judgment. These decision makers include customers, consultants, and members of industry groups, professional and technical associations, and the Project Management Office.
The project team is expected to provide expert judgment too. Members of the board and any other chosen experts also give their input on technical and management details. The members of the change control committee will use their own backgrounds, perspectives, and expertise to assist the project manager. They interpret work performance information and determine what action to take when managing change.
What is the purpose of the change control board?
Options:
Option 1: This option is correct. The change control board provides expert judgment on proposed changes and decides whether these changes should be approved or rejected.
Option 2: This is an incorrect option. The change control board isn't responsible for monitoring and controlling project activities. Its purpose is to assess and approve or reject change requests.
Option 3: This option is correct. The change control board generally has the final say on whether changes are accepted or rejected. In some circumstances, the project manager might make the decision and then inform the board. This probably wouldn't apply for a really significant change though.
Option 4: This option is incorrect. The project manager is responsible for updating project documents.
Correct answer(s):
The change control board usually either approves or rejects a proposed change. In some instances, it may feel it cannot make a decision right away and will put a change request on hold, pending further information. The criteria a change control board uses to make decisions are the feasibility of the change and whether the change will impact the project scope.
Select each of the criterion used by the control board for more information about it.
An example of a feasible change request may be a color palette change for a web site. This requires very little work and has no real impact on the project schedule, budget, and scope. So it would likely be approved.
This change is considered within scope because the color change doesn't add anything significant to the end product and so won't have a large impact on performance baselines.
On a graph that plots changes over time, scope is represented by a horizontal line part way up the y axis. As cumulative changes are plotted, they do not cross the scope line.
Another feasible change may be to upgrade the site to run both Java and Flash applets for advertisements. This change impacts the project scope, increasing the time and resources needed to complete the project. But if the change is sufficiently important to the project, it can be approved.
A request to change the functionality of the web site so it can process financial transactions is rejected as not feasible. This change would involve a further five months of development and testing time and a large cost increase. So it would significantly extend the scope of the project.
In this case, the customer may be persuaded to purchase this enhancement separately, as a new project.
If a change is not feasible, it is rejected. If the change is feasible, its impact on project scope is assessed. If a change is rejected at this stage, the change request is updated and filed. If the change is approved, its impact on scope determines what project documents will need to be updated.
A decision tree shows the paths a change request takes depending on whether it is considered feasible or not feasible. The first question the board asks is whether the change is feasible. If it is not feasible, it is rejected and updates are made to the change control documents. If the change request is feasible, it is reviewed in terms of its impact on project scope. If the scope is not affected it is approved and updates are made to project documents and change control documents. If the change does impact scope and is accepted, changes are made to project documents and change control documents.
Suppose the change request to upgrade the web site to run both Java and Flash applets for advertisements is approved.
This change will impact the scope of the project in terms of its functionality. This also impacts cost in terms of paying web developers to include the required coding. It may also take a few days longer and so affect the project schedule.
To counteract rises in costs and changes in schedule, further changes may have to be made to plans.
Match each description of a requested change to the appropriate category.
Options:
Targets:
When baselines can be adjusted at tolerable levels, the change request is considered feasible.
When a change request will require some adjustments to the project's performance baselines, it will impact the scope of the project.
When a change request doesn't require adjustments to the project plan or baseline performance, it is considered within scope.
If a change will require extensive adjustments to the baseline performance levels and could prevent a project from finishing on time and within budget, it is not a feasible change.
Correct answer(s):
Target 1 = Option A
Target 2 = Option B
Target 3 = Option C
Target 4 = Option D
Identify the missing question or step in the change control decision making process.
Description of decision tree follows.
The decision tree begins with a change request. The first question asked is if the change is within scope. If so, the change is approved. If not, the change is rejected.
Description ends.
Options:
Updates to the project plan occur only after a change is approved. And although the project sponsor's backing is important, it is not a step in the change control decision-making process. The change request must be assessed in terms of whether it's feasible, as well as whether it is within the project's scope.
Correct answer(s):
The outputs of the Perform Integrated Change Control process are approved change requests, change log, project management plan updates, and project documents updates.
Select each output of the Perform Integrated Change Control process for more information on the updates that need to be made.
Match updates to when they should occur. Each situation may have more than one match.
Options:
Targets:
Updates to change request status and to the change log must always be made, even when a change is rejected or given an on-hold status.
Baselines in the project management plan and forecasts for a project must be updated when a feasible change outside the project's original scope is approved.
Subsidiary plans often need to be updated to reflect approved changes that don't impact project scope but that affect relevant plans, such as those relating to quality management, human resources management, or risk management.
Correct answer(s):
Target 1 = Option D, Option A
Target 2 = Option E, Option B
Target 3 = Option C
So to manage change effectively, you need to maintain accurate and reliable performance measurement baselines, coordinate all processes impacted by the change, and update the project baselines to reflect any changes in product scope.
A customer focus group requests that a computer game you are developing include 3D graphics. This request comes late in the project and the change would prevent it from completing within specifications. The change board rejects the change.
What are the outputs of this change control process?
Options:
Option 1: This is a correct option. The decision to reject the change must be reflected in the change request status documentation.
Option 2: This option is correct. The decision to reject the change must be reflected in the change log. Decisions about all change requests must be entered in this log.
Option 3: This option is incorrect. Because the change was rejected, no changes to the project baseline are expected and no changes to the project plan are required.
Option 4: This option is incorrect. Forecast updates are only required when a change that impacts project scope is accepted.
Option 5: This is an incorrect option. Subsidiary plans need to be updated only when approved changes affect them. This can happen even if an approved change is feasible and within the project's scope.
Correct answer(s):
Inputs to the Perform Integrated Change Control process are change requests, organizational process assets, project management plan, work performance information, and environmental enterprise factors. As the project progresses, change requests may stem from monitoring and controlling processes as well as the executing processes.
The tools and techniques for the process are expert judgment, change control tools, and change control meetings. The change control board reviews and assesses change requests. It then approves or rejects the requests depending on their feasibility and impact on project scope.
Outputs of the Perform Integrated Change Control process include approved change requests, the change log, and updates to the project management plan and project documents.
After completing this topic, you should be able to
You've done everything, the deadlines have been met, and the project is over. Or is it?
If you take time to think through what has happened and formally bring activities to a clear conclusion at the end of a project, you'll reap the benefits.
"I was so relieved to get the project finished, I didn't think about what might need to be done to close the project properly. If I had finalized all activities across all project Process Groups, we wouldn't be dealing with problems after the project has finished."
Betty Park says
"I could have established procedures to verify and document the project deliverables. Doing so would have ensured that the transfer to operations went more smoothly."
Betty Park says
"I know I can't prevent problems from occurring in future projects, but I could have used the lessons I learned and revised processes. As it is, I'm back to square one with the new project I'm starting."
Betty Park says
When you formally close a project or a phase, you can avoid some of the problems Betty faced. Closing a project or phase confirms the project status. It also clarifies the successes and failures of the project. Closing properly releases resources and ensures completed project documentation is available for use in the future.
Select each benefit of the Close Project or Phase process for more information about it.
Close Project or Phase is the process of finalizing all the activities across all of the project management Process Groups to formally close a project.
Figure 3-1 of the PMBOK Guide Fifth Edition shows the Initiating processes lead to the Planning and Executing processes, which are iterative in nature, and which then lead to the Closing processes. Monitoring and Controlling processes occur while all the other processes are running.
The close process can also be used to end a phase of a multiphase project. This helps ensure that resources are released and that the deliverable is properly transferred to the next phase of the project.
In projects with more than one phase, the Process Groups will repeat for each phase. So the Closing processes for one phase lead to the Initiating processes for the next phase.
So the Close Project or Phase process ensures you transfer the completed deliverables as appropriate.
It coordinates the activities needed to verify and document project deliverables, formalizing the acceptance of deliverables by the customer or sponsor.
Finally, it is used to investigate and document the success or failure of a project or phase. If a project or phase is terminated before completion, it also identifies the reasons why.
The inputs to the Close Project or Phase process are the project management plan, accepted deliverables, and organizational process assets.
Isn't planning supposed to be done at the beginning of a project rather than the end? What would you use the project management plan for during the close of a project or phase?
Options:
The project manager doesn't update the project management plan at this stage and the plan is not used to set up the lessons learned database. The plan is used to compare planned performance baselines with actual results.
Correct answer(s):
Areas of the project management plan that are compared with actual results include the schedule, budget, and risks.
Select each area within the project plan for more information about how it acts as an input to the Close Project or Phase process.
To be used as inputs to the Close Project or Phase process, deliverables need to progress through several phases and processes before they reach the accepted deliverable stage. Follow along to learn more about each phase and process.
Project managers use the Direct and Manage Project Work process to oversee the creation of a product, component, or service. For example, a project team might create a software component during the work execution phase.
The software then passes through the Perform Quality Control process, where it is validated internally. For example, it passes through software testing.
Then during the Validate Scope process, the software is reviewed by an internal team to ensure it matches the project's scope statement. Stakeholders such as the customer or sponsor may also review and sign off on the product at this stage.
For example, a checklist for validating scope may have the items user interface, help files, and easy navigation.
Changes needed during the Validate Scope process are controlled through the Perform Integrated Change Control process. For example, keyboard shortcuts are added for key tasks within the software.
Finally, approval is obtained and the software becomes an "accepted deliverable" that's an input to the Close Project or Phase process.
Organizational process assets are the third and final input to the Close Project or Phase process. Some companies have phase and project closure guidelines, such as templates for performing project audits and evaluations.
Company guidelines may also include processes for performing subproduct – or component – validations and completed product validations. There are also likely to be guidelines for standard acceptance criteria.
What are the inputs to the Close Project or Phase process?
Options:
Option 1: This option is correct. In the Close Project or Phase process, performance baselines, such as the schedule and budget outlined in the project management plan, are compared against actual project results.
Option 2: This is a correct option. Once a product or other deliverable has been reviewed in terms of requirements and scope, the customer or sponsor signs off on the deliverable. Once the deliverable is accepted, it's used as an input in the Close Project or Phase process.
Option 3: This option is correct. Organizational process assets are used as inputs in the process. For example, company guidelines and processes can be used to ensure project evaluations are carried out correctly.
Option 4: This option is incorrect. Expert judgment is actually a tool used in the Close Project or Phase process, rather than one of its inputs.
Option 5: This option is incorrect. The transition of the deliverable is actually an output, rather than an input, of the Close Project or Phase process.
Correct answer(s):
There are three tools and techniques used in the Close Project or Phase process. These are meetings, expert judgment, and analytical techniques.
One of the main activities carried out during the Close Project or Phase process is ensuring the acceptance of deliverables. This involves meeting with members of the project team, the customer, and support personnel to confirm that all acceptance criteria have been met. You may also need to confirm that the deliverable has been accepted by the customer, and that all product sign-offs have been filed.
Expert judgment is chiefly used as you carry out administrative closure. This involves ensuring all the necessary paperwork is completed and properly archived. These documents include customer or sponsor sign-offs, finalized project files, and other project or phase records.
During administrative closure, you also gather lessons learned and archive project information for future use by the organization.
When performing administrative closure activities, use expert judgment to ensure the project or phase closure is performed to the appropriate standards.
How should project managers handle the situation if a project is canceled or closed early?
If a project is terminated, it's critical to document all information about it. This information may be needed if the project is reopened or if a similar project is started at a later date. For this reason, the administrative closure activities should be completed.
If a project is canceled or closed early, it is important that you investigate and document the reasons why. Reasons for early closure may include a change in business focus, technology, or legislation. There may also be changes in customer demands or in the market or business environment. Another reason for early closure is that the company may need resources to respond to a more urgent issue.
What are examples of subactivities related to administrative closure and confirming acceptance of deliverables?
Options:
Option 1: This option is correct. Consulting the project management plan is part of the acceptance of deliverables activity in the Close Project or Phase process.
Option 2: This is a correct option. Transferring the deliverables is part of the acceptance of deliverables activity of the Close Project or Phase process. During this activity, you ensure that products are transitioned either to the next phase or into operational use.
Option 3: This option is correct. Collecting and archiving project information is an administrative closure activity that occurs during the Close Project or Phase process.
Option 4: This option is correct. Acquiring signoff on deliverables is part of the acceptance of deliverables activity in the Close Project or Phase process.
Option 5: This option is incorrect. This activity is part of assessing the success of the project and does not occur during administrative closure or when you are confirming the acceptance of deliverables.
Option 6: This option is incorrect. The Verify Scope process occurs before the Integrated Change Control process and is not part of the Close Project or Phase process.
Correct answer(s):
The third main activity in closing a project or phase is to assess project success. This involves comparing actual project results to the planned results in the project management plan. This is the main activity during which analytical techniques are used, such as regression analysis and trend analysis.
A project manager gathers assessment information by performing any required project audits or evaluations. Typically a group of stakeholders carry out the assessment using this information. This group reviews the project management plan and deliverables to determine the degree of the project's success.
Selecting the link title opens the resource in a new browser window.
Job Aid
Access the job aid Closing Activities Checklist to review activities related to closing a project or phase, including one that's terminated or postponed.
A project assessment should answer several questions:
You have completed a project to create a new computer game.
What are examples of uses of the tools and techniques for the Close Project or Phase process?
Options:
Option 1: This option is correct. You may hold a meeting to confirm the acceptance of deliverables from a project or phase.
Option 2: This option is correct. Completing, gathering, and archiving sign-offs and project files is an aspect of ensuring proper administrative closure of a project or phase. You use expert judgment for these types of activities.
Option 3: This is a correct option. You need to gather information and use analytical techniques to assess the success of the project. This is an important activity in the Close Project or Phase process.
Option 4: This option is correct. Closing meetings are an aspect of assessing project success.
Option 5: This is an incorrect option. By the time the Close Project or Phase process starts, actual execution of project work is finished. If securing contracts was part of the project, you'd assess how well this was done as part of closing the project.
Option 6: This option is incorrect. The project plan does not take any further updates. You enter the results of assessing the project in a project report.
Correct answer(s):
The Close Project or Phase process helps confirm the closed status of a project or phase, and clarify its successes or failures. It also releases resources and ensures project documentation is complete.
The inputs of this process include the project management plan, the accepted deliverables, and organizational process assets. Using these inputs, you can ensure deliverables meet the proper criteria, project documents are gathered and archived, and the success of the project is assessed.
Expert judgment, analytical techniques, and meetings are used to ensure that all activities have been completed correctly.
Selecting the link title opens the resource in a new browser window.
Follow-on Activity
Access the follow-on activity Close Project Activities to review the procedures your company follows when closing a project or phase.
After completing this topic, you should be able to
You've done it. You've gotten through the project, and you think you've finished. But how can you be sure? You can be sure you're finished when you have two main outputs from closing the project – the transition of the final product, service, or result; and updates to organizational process assets.
Transitioning the project's final result means handing over its deliverables to whoever will control them next. This person or team will differ depending on several factors, including whether a product is at the end of a particular phase or at the end of the project, or whether the deliverable is a process improvement.
Select each transition situation for an example of how it may be handled.
You need to ensure that the product, service, or other result of a project or phase is formally accepted. This requires a signoff from relevant stakeholders.
A process asset signoff record may include space for the artifact name, description, document number, location where it is filed, names of the owner, reviewer, and approver, and any follow-up actions required.
For example, if there is a contract in place, you need formal signoff indicating that those who contracted the project have received and accepted the final product.
The acceptance must include a formal statement that the terms of the contract have been met.
A customer acceptance form may include an area to record the project name, creator of the form, version number, issues date, additional comments, reported shortfalls of final project outcomes, and signature lines for the sponsor, senior user, and project manager. There may also be an acceptance statement, such as "The project outcome has been measured against its acceptance and has been formally accepted on behalf of the customer. The project may now be closed."
Final product sign-offs generally include details of the product and an official signoff form that has to be signed by key stakeholders. Forms often differ depending on whether they are internal or external.
Select each form type for an example of it.
A project plan signoff form may indicate the attached project plan has been reviewed and is approved for execution by the undersigned, with a space for the project title, name and signature of project sponsor, and date.
The result of a project that develops or improves a business process is the document outlining the improvement. This should include a signoff document naming the process and owner, who it was reviewed and approved by, and any follow-up actions, such as the filing of signature copies.
Once a product or outcome has been formally signed off and transferred, the project manager is expected to notify relevant stakeholders of the transfer and that the product has been accepted.
What are the key elements of product transition?
Options:
Option 1: This option is correct. Formal sign-offs for project or phase outcomes must be signed by the customer or key stakeholders. Typically, your organization will have document templates for this purpose.
Option 2: This option is correct. Once a product has been signed off, it must be officially transferred to the next person or body responsible for it.
Option 3: This is a correct option. Once a product has been signed off and transferred, the project manager must notify relevant stakeholders of its status.
Option 4: This is an incorrect option. Updated process assets are an output of the Close Project or Phase process, but this is not an element of product transition.
Option 5: This is an incorrect option. Updating the lessons learned knowledge base is an activity of the Close Project or Phase process, but it is not an element of product transition.
Correct answer(s):
Updating organizational process assets at the close of a project helps you organize all the information, tools, experience, and documents from a project. Some of these may be used for future projects, so it's important that you make updates in these areas.
The organizational process assets that are updated during the Close Project or Phase process include project files, project or phase closure documents, and historical information.
Select each organizational process asset for more information about it.
Suppose you have recently completed the prototyping phase of a tool creation project. You begin updating organizational process assets by ensuring all formal acceptance documents for the prototype are completed and filed.
Next you review all the project documentation, such as the project management plan, scope, cost, and schedule baselines, and project calendars. You ensure these are complete and that the reports providing the end results of the phase are filed.
You ensure all phase closure documents, such as sign-offs and transfer reports, are completed and then enter historical information about the phase into the lessons learned database.
So outputs of the Close Project or Phase process include completed products or services, and updates to organizational process assets that are handed over to a new project phase or organizational function.
They also include completed signoff documents and archived project files and deliverables.
What are examples of outputs of the Close Project or Phase process?
Options:
Option 1: This is a correct option. Finalized products that are handed over to the customer are outputs of the Close Project or Phase process.
Option 2: This is a correct option. Finalized services that are handed over to the next phase or body are outputs of the Close Project or Phase process.
Option 3: This option is correct. Once a deliverable has been signed off and transferred, you need to notify relevant stakeholders of its status.
Option 4: This is a correct option. Archived project files and deliverables are an output of the administrative closure activities you perform in the Close Project or Phase process.
Option 5: This option is correct. Updated process assets that will be used again in the future are outputs of the closing process.
Option 6: This option is incorrect. Approved and rejected changes are an output of the Perform Change Control process.
Option 7: This is an incorrect option. Verified deliverables are an output of the Control Quality process, not the Close Project or Phase process.
Correct answer(s):
The outputs of the Close Project or Phase process include the transition of deliverables to the customer or a new phase, and updates to organizational process assets.
To transition a product, you need to obtain formal sign-offs for the product, officially hand the product over, and inform stakeholders of the product's acceptance and transfer.
Updating organizational process assets provides useful information and tools for later phases or projects. The organizational process assets that can be updated during the Close Project or Phase process include project files, project or phase closure documents, and historical information.