Monitoring and Controlling Project Scope (PMBOK® Guide Fifth Edition)

Course Overview

Read the Course Overview.

Validate Scope

Control Scope

Course Overview

Change is everywhere, and projects confront it at every turn. Over the course of a project, deliverables will evolve in response to new stakeholder requests and feedback about completed stages. The task facing the project manager is to accommodate changing circumstances without undermining the project. To meet that challenge successfully, managers must reconcile requests for changes with the realities imposed by the project's original scope and timetable.

Before a project ends successfully, all stakeholders must know that their requirements and expectations have been met completely.

The Validate Scope process provides the tools and techniques that enable stakeholders to do this.

While managing a project, you need to control scope to ensure that the work is completed on time and within budget.

The project manager does this using the tools and techniques of the Control Scope process.

The Control Scope and Validate Scope processes are part of the Project Scope Management Knowledge Area and the Monitoring and Controlling Process Group.

Graphic

The other processes in the Project Scope Management Knowledge Area are Plan Scope Management, Collect Requirements, Define Scope, and Create WBS, which are all Planning processes.

Keep in mind that there are two types of scope.

Project scope is the work required to produce the deliverables.

Product scope refers to the features and functions of the product, or the characteristics of the service, you produce.

Graphic

For example, the product scope of a smartphone might include e-mail, video and music capability, calculator, and calendar.

Reflect

How do you think project and product scope are related?

Enter your thoughts in the text box provided and then select the Compare button for an answer.

Write down your response or enter it in a text file in your word-processor application (or in a text editor such as Notepad) and save it to your hard drive for later viewing and for comparison with the alternate opinion that follows.

Project and product scope

Changes to product scope always create changes to project scope, because the work required to make the product according to specification also changes. If you change the product, however slightly, you impact the work required to make the product.

Imagine a project to build a high-performance car engine. The project has been planned entirely around the engine specifications. Now suppose you add a feature to improve fuel consumption. This changes the project scope by adding the extra work required to effect the change.

The Validate Scope process takes place after the initial completion of project deliverables. The deliverables are then ready for stakeholder validation. This involves two main activities on the part of stakeholders: inspection and formal acceptance.

The Control Scope process ensures that all requested changes are processed through an integrated change control system. This involves using inputs from the planning and execution stages to detect scope creep and decide how to handle variance.

In this course, you'll learn how to monitor and control scope using the Validate Scope and Control Scope processes.

You'll learn about stakeholder inspections, what's required for deliverables to be formally accepted, and what to do when deliverables don't pass a verification check.

You'll learn about the inputs to the Control Scope process and how to use them effectively.

You'll also find out about the outputs of the process and the purposes they serve in controlling scope.

Finally, you'll learn about the use of change requests in managing scope, and how approved changes can impact other areas of a project.

Back to top

Inspecting Deliverables

Learning Objectives

After completing this topic, you should be able to

1. The Validate Scope process

After much hard work, your team has finally completed the project it began a month ago. The product is working, the documentation has been completed, and everyone is finally ready to put their feet up and relax. But has the team really finished everything it needs to do?

One answer to this question lies in the Validate Scope process.

Graphic

The Direct and Manage Project Work process produces deliverables that are checked during the Control Quality process. The verified deliverables move to the Validate Scope process. Accepted deliverables go to the Close Project or Phase process.

Project managers and stakeholders use this process to confirm that project deliverables are accepted as meeting requirements. A project is incomplete if this hasn't occurred.

Before scope validation can take place, the project deliverables must be clearly identified. This is done during the planning stages of the project as a result of several scope-related planning processes:

Graphic

An excerpt of Fig. 3-3; PMBOK® Guide - Fifth Edition shows that the Initiating Process Group links to the Planning Process Group, which links to project documents and to the Executing and Closing Process Groups. Project documents also link to the Executing Process Group, and the Executing Process Group links to project documents.

The Planning Process Group, project documents, and the Executing Process Group stand in a reciprocal relationship with the Monitoring and Controlling Process Group. This Process Group links to the Closing Process Group.

The outputs from these processes – the requirements management plan, scope management plan, project scope statement, and scope baseline – become part of the project management plan, which is used to manage and control scope throughout the execution of the project.

Reflect

Think of a recent project you've worked on.

Why do you think it's important for the project team to verify scope internally once they've finished creating deliverables?

Enter your thoughts in the text box provided and then select the Compare button for an answer.

Write down your response or enter it in a text file in your word-processor application (or in a text editor such as Notepad) and save it to your hard drive for later viewing and for comparison with the alternate opinion that follows.

Why it's important to verify scope internally

What if you hand over the deliverables to the stakeholders for validation, but have missed something important?

It's important to verify scope internally first so that you can avoid any embarrassment that may arise if your team has missed something. So you should answer the questions, "Have we completed all deliverables?" and "Do all deliverables meet requirements?" before handing deliverables over to stakeholders for review and validation.

The Validate Scope process is important during final delivery of a project because a project isn't complete until stakeholders accept the deliverables. They compare the deliverables with their requirements and the project management plan. When they're satisfied, they should confirm their acceptance in a formal, written statement.

A restaurant has hired an advertising firm to put together a short promotional DVD for prospective investors.

The project team has completed the project activities, but before the project work can be considered complete, the project manager, along with the project team and stakeholders, has to validate scope.

The Validate Scope process for this project consists of two main tasks:

Question

What are the main activities that take place during the Validate Scope process?

Options:

  1. Stakeholders inspect project deliverables
  2. The project manager defines the project scope
  3. Stakeholders formally accept deliverables
  4. The project manager inspects the quality of each deliverable

Answer

Option 1: This is a correct option. Stakeholders look at each deliverable, ensuring it meets their requirements and satisfies the requirements listed in the scope baseline and requirements documentation.

Option 2: This option is incorrect. Although this step is part of Project Scope Management, it happens as part of the Planning Process Group – before project work starts. The Validate Scope process gets underway only once deliverables have been created.

Option 3: This is a correct option. After stakeholders have validated all the deliverables, they confirm their acceptance in a formal, written statement.

Option 4: This is an incorrect option. Inspecting the quality of each deliverable is part of the Control Quality process. While Control Quality activities can be performed in parallel with Validate Scope activities, it is a separate process.

Correct answer(s):

1. Stakeholders inspect project deliverables
3. Stakeholders formally accept deliverables

2. Inputs to Validate Scope

Before scope can be validated, it's important to know what to compare project results against. So, what does the Validate Scope process use to determine if a project has met expectations?

Scope validation is essentially a process of inspection and acceptance. During the scope planning process, the stakeholders identified and agreed to the project's requirements. As the work progresses and various deliverables are completed, stakeholders want to compare those completed deliverables against the project requirements and acceptance criteria.

Graphic

Documents used in scope validation include the scope baseline components, such as the project scope statement and WBS dictionary, and a checklist for evaluating completed deliverables.

The inspection of deliverables – also known as an audit, review, product review, or walkthrough – can include three activities:

Question

Now that you know the kind of work involved in the Validate Scope process, which items do you think are inputs into the process?

Options:

  1. Project charter
  2. Verified project deliverables
  3. Requirements documentation
  4. Project schedule
  5. Project management plan

Answer

Verified project deliverables, the project management plan, and requirements documentation are all inputs to the Validate Scope process. The project charter and project schedule are not inputs to the Validate Scope process.

Correct answer(s):

2. Verified project deliverables
3. Requirements documentation
5. Project management plan

One of the inputs used to validate scope is the project management plan, which contains the scope management plan and the scope baseline. These documents contain the process for how formal acceptance of completed project deliverables will be obtained and details about the project scope, major deliverables, assumptions, and constraints.

Verified deliverables are another input. They are project deliverables that were completed and checked for correctness during the Control Quality process. Verified deliverables are the subject of scope validation.

In addition to the project management plan and verified deliverables, there are three more inputs to the Validate Scope process:

Select each input to find out more about its contents.

Requirements documentation
Requirements documentation sets out project requirements, product requirements, technical requirements, and any other requirements that the project must meet.

Requirements traceability matrix
The requirements traceability matrix links each requirement to its origin. When project progress is reviewed or project scope is adjusted, the matrix is updated.

Work performance data
The work performance data that is used in the Validate Scope process may include data about how well the deliverables comply with requirements, the number and severity of any nonconformities found by the quality control team, or the number of quality tests that were performed on each deliverable.

A team has completed a project to develop a course on basic web design. The project manager gathers inputs to prepare for validating scope with the help of the project team and stakeholders.

The inputs are the project management plan, the requirements documentation, the requirements traceability matrix, the verified deliverables, and the work performance data related to the product.

Graphic

Examples include the completed CD containing the "Starting out in web design" program and a quality testing report.

Select each input to find out about its content for the project.

Verified deliverables
The verified deliverables of the project are the course – contained on a CD – and associated documentation, both for end users and stakeholders.
Project management plan
The project management plan specifies that the course should introduce web site basics and cover topics on designing pages, graphics, and basic coding. Search engine optimization and implementing multimedia on web sites fall outside the scope of the course.

The scope management plan indicates that formal acceptance of the course will be obtained following a walk-through review with stakeholders from the customer organization.
Requirements documentation
The stakeholders have specified the presentation style of the course in the requirements documentation. The course must contain text, graphical, and voiced instruction.
Requirements traceability matrix
Among other required components, the requirements traceability matrix has entries for text, graphical, and voice instruction. One of the entries indicates that graphic changes must occur on every page of the course. This links back to the requirements for graphics in the course.
Work performance data
An important input for the validation process is the record of review comments and fixes that were made during incremental customer reviews along the way. These records will provide a reminder of how the course evolved from the original scope statement.

Question

Which items are inputs to the Validate Scope process?

Options:

  1. Requirements documentation
  2. Project budget
  3. Project management plan
  4. Project time line
  5. Verified deliverables
  6. Requirements traceability matrix
  7. Work performance data

Answer

Option 1: This option is correct. Requirements documentation identifies all requirements and their relative priorities. To validate scope, stakeholders will compare project deliverables to these requirements.

Option 2: This is an incorrect option. Although the project budget affects scope, it's not an input to the Validate Scope process. During the process, the focus is on verifying the scope of deliverables.

Option 3: This is a correct option. The project management plan is an important input to the Validate Scope process as it includes the scope management plan and the scope baseline. The scope baseline is made up of the project scope statement, WBS, and WBS dictionary.

Option 4: This option is incorrect. Although the Validate Scope process begins at a scheduled time, the project time line is not an input to the Validate Scope process. It doesn't affect whether deliverables already created by the project team meet specified requirements.

Option 5: This option is correct. To validate scope, stakeholders need to check the actual project deliverables to confirm they meet requirements.

Option 6: This is a correct option. The requirements traceability matrix must be updated when project progress is reviewed. Thus, in the Validate Scope process, if the project scope is adjusted, the matrix must be updated.

Option 7: This is a correct option. Work performance data can provide an important context for the final state of the deliverables and give insight into how the project has gone in terms of creating the product or service.

Correct answer(s):

1. Requirements documentation
3. Project management plan
5. Verified deliverables
6. Requirements traceability matrix
7. Work performance data

As stakeholders inspect project deliverables, they may find problems with deliverables or areas that have been overlooked. Any defects or problems should be captured so they can be addressed.

With products that are electronic in nature – like software programs or documents – issues can be recorded using something as simple as a spreadsheet, or a more elaborate option may be used, like an online bug-tracking system.

When the product is a physical object, stakeholders can log problems in writing, using a checklist or some type of comments form, such as a survey.

3. Validate Scope versus Control Quality

Question

Given the types of inspecting activities that are performed during scope validation, which project management process do you think is similar to the Validate Scope process?

Options:

  1. Collect Requirements
  2. Control Quality
  3. Define Scope
  4. Create WBS

Answer

Validating scope is similar in nature to Control Quality, except that the Validate Scope process is only concerned with whether all the necessary requirements are included, and that deliverables are accepted. Quality control activities make sure that the deliverables are correct and meet the quality requirements outlined in the quality management plan.

Correct answer(s):

2. Control Quality

Although the Validate Scope and Control Quality processes have much in common, they are not the same. The project manager needs to be clear about the differences between them.

Select each process to find out more about it.

Graphic

A table that compares the Validate Scope process to the Control Quality process. The first column is titled Category, and the three categories form the rows: purpose, performed by, and reviewed against. Each intersecting cell contains information related to each category as it applies to each of the processes.

Validate Scope
The Validate Scope process aims to ensure that project deliverables meet requirements. The project manager reviews the verified deliverables with the customer or sponsor to ensure that they are satisfactorily completed. The customer or sponsor either accepts or rejects the deliverable based on whether it meets the acceptance criteria outlined in the requirements documentation.
Control Quality
The Control Quality process aims to identify and eliminate the causes of poor quality with products or processes associated with the deliverables. The Quality Control Department and project management team carry out this process and ensure that project deliverables meet the predefined quality standards and requirements for final acceptance.

The relationship between scope validation activities and quality control activities needs to be thoughtfully planned and managed.

The way the processes are coordinated depends on the nature of the project, the requirements of the stakeholders, and the monitoring and control needs of the project manager.

For example, a customer has hired a software development company to develop a custom piece of software.

Select each process to find out how it's applied to this project.

Graphic

A table that compares the Validate Scope process to the Control Quality process. The first column is titled Category, and the three categories form the rows: purpose, performed by, and reviewed against. Each intersecting cell contains information related to each category as it applies to each of the processes, specific to the software development project.

Validate Scope
Before the finalized product and project work can be considered officially signed off as complete, the project manager must review the verified deliverables with the customer or sponsor. If they are satisfactorily completed, formal acceptance will be provided by the customer or sponsor using the methods specified in the scope management plan.

Verified deliverables are reviewed against two requirements: there is one software module per job category, and all modules are included in the software.
Control Quality
The quality control team performs quality reviews at the close of each project phase.

Quality is measured against two requirements: quality checklists to verify all modules function properly, and the quality control team must ensure that the software meets the organization's quality standards and policies.

In a different case, a company has initiated an internal project to develop and roll out new financial procedures for the organization.

Select each process to find out how it's applied to this project.

Graphic

A table that compares the Validate Scope process to the Control Quality process. The first column is titled Category, and the three categories form the rows: purpose, performed by, and reviewed against. Each intersecting cell contains information related to each category as it applies to each of the processes, specific to the financial procedures project.

Validate Scope column
The Validate Scope process is intended to ensure that the procedures meet customer or sponsor requirements.

The chief financial officer is the sponsor. He participates in the scope validation review with the project manager when deliverables are complete.
The Validate Scope process is reviewed for all areas of the company covered by procedures.
Control Quality column
The Control Quality process is intended to ensure that there are no loopholes in the procedures.

The quality control team performs product and documentation testing throughout the development phase, but is not involved during the rollout phase.

Quality is measured against two requirements. All procedures must have accessible reporting methods built into the system.
The Control Quality process is measured against the requirements that all procedures are in line with statutory financial standards, and that procedures protect the company from legal liability should something go wrong.

There are several key differences between the Validate Scope and Control Quality processes:

Supplement

Selecting the link title opens the resource in a new browser window.

Job Aid

Access the job aid Validate Scope versus Control Quality for more information on the differences between these processes.

Question

A software company is designing a management system for a city's Disaster Operations Department.

Match each characteristic or activity to the corresponding process. More than one characteristic or activity may match to a process.

Options:

  1. A quality assurance officer on the software company's project team carries out the process
  2. The system is confirmed to contain operations tracking, budget tracking, basic administration, and reporting functions
  3. Reporting performance is measured against the benchmark of two minutes to generate each report
  4. The project manager and the customer carry out the process

Targets:

  1. Validate Scope
  2. Control Quality

Answer

The Validate Scope process is performed by the project manager with the customer or sponsor. It confirms that requirements have been met.

The Control Quality process is performed by members of the quality control team. It involves reviewing deliverables and progress against quality standards that have been predefined.

Correct answer(s):

Target 1 = Option B, Option D

Target 2 = Option A, Option C

4. Summary

The Project Scope Management Knowledge Area includes the Validate Scope process, in which the customer or sponsor inspects each project deliverable to ensure it meets their requirements.

This process is essentially an inspection. The project manager with the customer or sponsor compare completed deliverables against the project requirements and acceptance criteria. Inputs to the process are the verified deliverables, project management plan, requirements documentation, work performance data, and the requirements traceability matrix.

Although both the Validate Scope and Control Quality processes have similarities, they have different purposes, are performed by different parties, and occur at different times. Activities in both processes should be carefully planned and coordinated.

Back to top

Documenting Acceptance and Changes

Learning Objective

After completing this topic, you should be able to

1. Outputs of the Validate Scope process

Validating scope is not just about satisfying yourself that the deliverables of your project have been achieved. You need official approval from project stakeholders as well. Consider a project team that has recently finished installing a computer network. At every stage, the client seemed happy with the work. The project manager seals the deal with a handshake, confident that he can begin closing the project. But the client phones a few days later with a long list of changes.

Question

Consider the project manager's situation.

How important do you think it is to receive a signed statement from stakeholders that confirms their acceptance of deliverables?

Options:

  1. Very important
  2. Good to have, but not vital
  3. Unimportant

Answer

Option 1: You've indicated it's vital to get formal sign-off on deliverables from stakeholders. That's right. Without this, a project can't be properly completed. You may have to deal with continual demands for amendments and further work later on.

Option 2: You say it's good, but not critical, to have stakeholders confirm their acceptance of deliverables in writing. But think about what not having formal, written acceptance might mean further down the line. A stakeholder might agree to accept your work verbally, but come back weeks or even months later with new demands. You'd have no way to show the project was formally closed.

Option 3: You've indicated that it's not important to get written acceptance of deliverables. You might want to think again about how important getting stakeholders' formal sign-off is. Without any kind of written acceptance of deliverables, you might think a project has closed, but stakeholders might not. This could mean a client keeps making demands indefinitely.

So the best practice when managing a project is to get stakeholder agreement in writing when the project deliverables meet requirements.

Formal written acceptance of deliverables is part of the Validate Scope process, in addition to reviewing verified deliverables with the customer or sponsor.

This acceptance is the main output of the Validate Scope process.

Graphic

For example, validating scope may mean ensuring software meets requirements by reviewing the final product with the customer and obtaining formal acceptance. Internal scope verification is carried out by the project manager with the customer. One module per job category and all modules included in software will be validated.

If the project manager in the network installation example had completed the process properly, he would have received his client's official sign-off. It would have been clear to everyone that the project was in the closing stage. So he would have been spared the surprise phone call and the list of new demands.

It's vital that you keep an official record of the acceptance of deliverables by relevant stakeholders. This protects you from later claims that the project was not completed satisfactorily.

Once you have written acceptance of project deliverables, it's important to file the acceptance and to update any logs or project documents. This ties up any loose ends and ensures nothing is overlooked.

Project documents updates are the second output of the Validate Scope process. If the scope of a project has changed, you need to reflect this change in all documents that define the product or report the status on product completion. For example, you'd update the requirements documentation if an inspection discovers that the product would function more effectively if the specifications were altered.

Question

What do you think should happen if stakeholders find that some project deliverables don't meet requirements and ask for changes?

Options:

  1. Reject all stakeholders' requests for changes because they fall outside the project's scope
  2. Begin an official change request process for reviewing proposed changes
  3. Ensure stakeholders identify required changes clearly
  4. Implement all stakeholders' requests for changes as soon as possible

Answer

Option 1: If stakeholders have legitimate objections, it's important to address these. Proposed changes should be reviewed, and approved changes should be implemented.

Option 2: As with any changes to the project, the changes stakeholders require should be officially reviewed. Only approved changes should then be implemented.

Option 3: Scope validation takes place throughout a project from the time the first deliverables are completed. Often, changes to one deliverable affect changes in subsequent deliverables. The earlier you can get acceptance, the better.

Option 4: Not all stakeholders' requested changes are necessarily valid or would be beneficial. Before requested changes are implemented, they should be evaluated, and only approved changes should go ahead.

Correct answer(s):

2. Begin an official change request process for reviewing proposed changes
3. Ensure stakeholders identify required changes clearly

That's where another output of the Validate Scope process – change requests – comes into play.

Graphic

A change request may include the project name, requestor, project manager, request description, reason for request, risks if not implemented, and priority of request.

As stakeholders inspect deliverables, they should use a log or another tool you supply to record issues and any necessary changes they feel are warranted.

The project manager reviews the results of the inspection. If any stakeholder feels a change is required, the manager then compiles this information into a change request.

Graphic

For example, a high priority change request for a network upgrade project has been made by Jill Thomas who requests that security codes by at least seven characters, since current security settings are too easily cracked. The risk is that information on the computer systems could be stolen if security is not tightened.

Any change request triggers the integrated change control system that is in place for the project. The request is evaluated and either approved, deferred, or rejected.

The decision is recorded, and only approved changes are implemented. Once this has happened, the project manager inspects deliverables again – with the customer or sponsor – to validate scope.

Graphic

A flow diagram shows that a change request is either approved, deferred, or rejected. If the change is approved, the decision is recorded, the approved change is implemented, and the deliverable is reinspected by the stakeholder.

Question

Why do you think a customer or sponsor might reasonably decide a change to deliverables is necessary?

Options:

  1. All pre-agreed requirements have been met but changes would improve the quality of the project's results
  2. One or more of the deliverables don't meet the specified standards
  3. The customer has decided to abandon the project but would like to redirect your team's efforts into a new project
  4. A new opportunity or one not realized at the outset of the project makes change desirable

Answer

Option 1: This is a correct option. It would sometimes be reasonable to ask for a change, even if the deliverables are technically completed as specified.

Option 2: This is a correct option. If targets are not met, it would be reasonable to ask for more work to be done in order to reach minimum standards. If a motherboard is incompatible with a chip that the client specified, the client would be justified in sending a change request asking you to rectify the problem.

Option 3: This option is incorrect. A change request would not be required in this situation – the current project is over.

Option 4: This is a correct option. Say a more advanced type of chip is released. It might prompt a change request asking you to incorporate the new technology into your motherboard, making it more desirable to customers.

Correct answer(s):

1. All pre-agreed requirements have been met but changes would improve the quality of the project's results
2. One or more of the deliverables don't meet the specified standards
4. A new opportunity or one not realized at the outset of the project makes change desirable

Whatever the reason for wanting a change, a stakeholder should always submit a change request form outlining the desired change and the reasons for it.

Graphic

Section A of change request form is filled in by the requestor. It includes these row headers: Date, Project name, Requestor, Project manager, Request description, Reason for request, Risks if not implemented, and Priority of request - Low, Medium, High, or Critical.

The project manager should then assess the request and the impact the change will have and document the details of the request.

Graphic

Section B of a change request form is filled out by the project manager and includes these row headers: Work required, Resources required, Expected duration, Dependencies, Additional cost, Contracts affected, Risks if followed through, Triple constraints impacted, Project manager's recommendation, Signature, and Date.

If a change control board is responsible for authorizing changes, the manager should also include a recommendation before passing the change request on to the board.

Graphic

This information would go in the row called Project manager's recommendation.

In the case of the network installation project, during the scope validation, the customer noted that the network protection security requirements were still below the necessary threshold.

Graphic

In this case, the date on which the change request form is filled in by the requestor is August 19. The project name is Network upgrade. The requestor is Jill Thomas and the project manager is Tyrone Oswald.

If security codes remain only four characters long, any benefits of the new network will be offset by poor security. The client completes a change request form, and the project manager reviews the request.

Graphic

In this example, the requestor has described the requested change as, "Though initial specifications called for security codes four characters in length, these codes must be at least seven characters in length for security reasons." The reason for the change is given as, "Current security settings are too easily cracked." The risk of not implementing the change is recorded as, "The information on our computer systems could be stolen if we do not tighten security." The request has been assigned a high priority.

So the first section of the change request form is completed by the stakeholder requesting the change – also known as the requestor.

In the bottom section, the stakeholder describes the change that she wants to be made, the reasons for the request and the risks it will address, and the request's priority – or level of importance.

Reflect

The second section of the change request form is filled out by the project manager.

Why do you think it's necessary for the project manager to review change requests when the final decision on whether to approve a change is often left to a change request board?

Enter your response in the text box provided and then select the Compare button for more information.

Write down your response or enter it in a text file in your word-processor application (or in a text editor such as Notepad) and save it to your hard drive for later viewing and for comparison with the alternate opinion that follows.

Why the project manager's input is necessary

Generally, the project manager has a good understanding of the project as a whole. So even if a change control board has the final authority to approve or reject a requested change, the manager should provide an informed judgment about whether it should go ahead. This should include what risks are involved and how the change could impact project scope.

The section of the form completed by the project manager outlines what impact the requested change will have in terms of the work, resources, extra time, and extra costs required. It identifies dependencies, or factors that have to be in place before the change can be made. It also outlines any risks associated with making the change, and its likely total impact on the triple constraints of cost, duration, and quality.

Graphic

In Section B of the change request form, the work required is given as, "Startup and login process must be reprogrammed." Resources required is given as one full-time programmer. Expected duration is one week. Dependencies are Availability of original programming team.  Additional cost is given as $3,500. Contracts affected is given as "Network upgrade contract." Risks if followed through is given as "Some current data on system may be lost if user profiles are changed." Triple constraints impacted is given as, "This will add to the duration, and therefore the costs, of the project. However, this is necessary to ensure the quality of the final product." The project manager's recommendation is to proceed. The section also includes the project manager's signature and the date.

Finally, the project manager includes a recommendation for either accepting or rejecting the request, and signs and dates the form.

Graphic

In the sample form, the project manager's recommendation is to proceed. The form is dated August 21.

Question

The network in the installation did not meet the network protection security requirements. The client completed the change request form and the Project Manager made a recommendation.

What should happen next?

Options:

  1. The project manager should approve the change request
  2. Rework the deliverables without requiring formal change requests
  3. Have the Change Control Board review the change request

Answer

Option 1: This is an incorrect option. The project manager made a recommendation; however, it is up to the Change Control Board to officially determine whtether or not the change request is approved or rejected.

Option 2: This is an incorrect option. All changes should be controlled through a clearly defined change control process. This applies even if change requests are made because original acceptance criteria or requirements weren't met.

Option 3: This is the correct option. Change requests have to reviewed first by the Change Control Board as part of the Perform Integrated Change Control Process before being approved or rejected.

Correct answer(s):

3. Have the Change Control Board review the change request

In the network installation project example, the Change Control Board will review the Project Manager's recommendation and decide whether to approve, reject, or deferred based on the recommendations and circumstances for not meeting the network protection security requirements.

If the change request is approved through Perform Integrated Change Control, the approved change requests will be implemented during the Direct and Manage Project Work process.

If the Change Control Board decides to reject the change request, the client may decide to pursue legal action if there was a breach in the contract.

Supplement

Selecting the link title opens the resource in a new browser window.

Job Aid

Access the job aid Sample Change Request Form as a guide for creating your own change request template.

If the Project Board defers the change request the company working on the network installation project could try to find an alternative way of satisfying the client.

For instance, it might not be feasible to totally reprogram the security codes, but it could be possible to program a system to overlay the original security codes.

If the client agrees, the original change request can be modified and resubmitted before it's approved or rejected.

When it comes to managing change requests, the bottom line is that changes should represent a net benefit to the organization. At the Validate Scope stage, you should only approve changes relating to defects in the product or representing gain for the project.

Once a change request has been approved, the project team must implement the change.

The project manager will inspect deliverables with the customer or sponsor again, and if they're satisfied, the deliverable will be formally accepted.

The final output of the Validate Scope process is work performance information. This information usually takes the form of progress reports to stakeholders.

Examples of progress you may report include which deliverables have started, the current status of other deliverables, and the date when you expect deliverables to be signed off.

Work performance information can also be used to justify change requests.

Question

What are the outputs of the Validate Scope process?

Options:

  1. A list of project flaws
  2. Accepted deliverables
  3. A checklist of deliverables
  4. Change requests
  5. Project documents updates
  6. Work performance information

Answer

Option 1: This is an incorrect option. During the Validate Scope process, stakeholders check project deliverables against project requirements. They may detect potential flaws and document change requests as a result. However, the process isn't concerned with evaluating all possible flaws in a project; its focus is on securing acceptance of deliverables.

Option 2: This option is correct. The main purpose of the Validate Scope process is to obtain formal acceptance of project deliverables from stakeholders.

Option 3: This is an incorrect option. The Validate Scope process is concerned with securing acceptance of project deliverables, rather than with itemizing them.

Option 4: This is a correct option. Official change requests are one of the outputs of the Validate Scope process. As a result of inspecting deliverables, stakeholders may log change requests they feel must be implemented before they sign off on the deliverables.

Option 5: This is a correct option. The Validate Scope process may request changes before stakeholders formally accept a project's deliverables. If this happens, project documents, such as the project scope statement, must be updated.

Option 6: This is a correct option. A project manager will typically submit performance reports to stakeholders as a result of carrying out the Validate Scope process. The report may indicate which deliverables have been validated and which still require changes.

Correct answer(s):

2. Accepted deliverables
4. Change requests
5. Project documents updates
6. Work performance information

2. Summary

The Validate Scope process has four outputs: the accepted deliverables, project documents updates, change requests, and work performance information. It's important to obtain formal, written acceptance of deliverables from stakeholders before a project closes.

You need to document the changes stakeholders ask for in change request forms and deal with them through a formal integrated change control system. And work performance information that results from validating scope may be used to communicate information about validation activities, or in submitted change requests as a result of this process.

Supplement

Selecting the link title opens the resource in a new browser window.

Follow-on Activity

Access the follow-on activity Interview Response Form for a set of questions about handling scope changes that you can ask experienced project managers.

Back to top

Requirements for Scope Control

Learning Objectives

After completing this topic, you should be able to

1. Purpose of the Control Scope process

A successful project is one that meets all the planned project requirements and objectives. But during a project, changes are inevitable, and these changes can sometimes affect those requirements and objectives. The Control Scope process can help you manage changes to a project's scope and so keep it on target to meet requirements and objectives.

Graphic

A Control Scope flowchart displays a variance analysis field. It contains the Assess unit, which flows into the Review unit. The review unit then branches into the units Approve, Defer, and Reject.

Control Scope is the last of the processes in the Project Scope Management Knowledge Area. It also falls in the Monitoring and Controlling Process Group.

Graphic

The other processes in the Project Scope Management Knowledge Area are Plan Scope Management, Collect Requirements, Define Scope, and Create WBS, which are all Planning processes. The other Monitoring and Controlling process is Validate Scope.

Using this process, you monitor the scope of a project and manage changes to it.

You use the Control Scope process to manage two kinds of scope change: unmanaged change and managed change. Unmanaged change, often referred to as scope creep, is not planned and can be problematic. Managed change, which is the result of approved change requests from project team members or stakeholders, is beneficial.

Select each type of change to find out more about using Control Scope to manage it.

Unmanaged change
Unmanaged change occurs when a project deviates from its planned scope. It's also known as variance. It can negatively impact the budget and schedule, or cause a project to fail in meeting its objectives. The Control Scope process helps you detect unmanaged change, find ways to resolve it, and limit its impact on the project.
Managed change
You use managed change to correct scope creep, or adjust the scope via a change request, which can arise during daily monitoring. Generally, project managers and sponsors reject all requests by default at this point in the project, unless the change has a proven benefit. The Control Scope process ensures that only beneficial changes are approved.

If you detect variance early, it can often be reduced by small, low-impact operational changes.

If change goes unchecked, you may be left with no option but to request a scope change in order to meet the project's objectives.

You are the project manager on a web site development project. The first deliverable is the site itself. The creation of the home page is a work package related to that deliverable.

Graphic

The WBS for the web site development project has three deliverables: Planning, Site, and Rollout. The Site deliverable consists of the Home page and Other pages work packages.

The customer will validate the home page so that the look and feel is approved before you develop the rest of the site.

You notice that the quality of the graphics and the interface overall is much better than you expected. In fact, it's a lot better than what you budgeted for.

You check the specifications in the scope statement and notice that the graphic designer exceeded the agreed upon quality standards. When you ask him for an explanation, he says he decided to put a little extra effort into the design, and he thinks it now looks much better than if he'd followed the specifications. The result, however, is a home page phase that ran 12% over budget and took longer to design. If the rest of the site is developed in this way, it will lead to significant overruns. So what should you do?

Graphic

A quality statement describes the look and feel aesthetic quality of the web site.

It looks like you've got a case of scope creep on your hands. Project managers face situations like this one on a fairly constant basis.

Perhaps it's a customer who's always pushing for more, or someone on the team who means well but goes beyond the specifications and doesn't understand how small, unapproved changes can affect the whole project.

The Control Scope process helps you avoid this type of situation.

Question

You're the project manager for a project to build a cell phone camera application that will allow a digital zoom of 500%. During software development, one of the developers figures out a way to have the zoom go to 800%, although it will take ten extra hours to achieve. To the developer, it seems worthwhile, so he starts implementing this.

Does this situation seem like scope creep to you?

Options:

  1. Yes, this situation represents scope creep
  2. No, this situation doesn't represent scope creep

Answer

This situation represents scope creep because an unapproved scope change has taken place. The developer should have submitted a change request to authorize the scope increase. If the customer now rejects the change, it may need to be reversed.

Correct answer(s):

1. Yes, this situation represents scope creep

Part of managing scope change is controlling the effect of changes on the rest of the project.

To do this, the Control Scope process ensures that change requests that arise from monitoring the project go through the Perform Integrated Change Control process.

Controlling scope in this context means coordinating scope changes with other control processes, specifically those for controlling costs, schedule, quality, and risk.

It also entails ensuring that the recommended corrective actions are implemented fully and correctly.

During the web site development project, a project team member identifies an enhancement to the site's functionality and takes the initiative to develop it. You identify this scope creep. In addition, the customer requests a scope change.

Select each type of change in the web site design project to learn how best to control it in this situation.

Scope creep
As part of the Control Scope process, you put a stop to the scope creep by stopping the work on the enhancement. The enhancement deviates slightly from the specification, so the problem can be corrected quickly and simply without a scope change.
Scope change
The client requests a new feature that will require a different design. This request constitutes a major scope change and will increase the cost and time required for the project. The sponsor agrees to increase the budget and authorizes the change.

Question

For what purposes do you use the Control Scope process?

Options:

  1. Creating the work breakdown structure
  2. Detecting and correcting scope creep
  3. Detecting scope creep through stakeholder inspection of deliverables
  4. Managing change requests to prevent detrimental changes to scope

Answer

Option 1: This option is incorrect. The work breakdown structure is created during the Create WBS process, not the Control Scope process.

Option 2: This is a correct option. The Control Scope process provides the tool that enables you to detect scope creep, or variance.

Option 3: This is an incorrect option. Stakeholders inspect deliverables as part of the Validate Scope process.

Option 4: This option is correct. The Control Scope process enables you to manage change requests so that only beneficial and approved changes take place.

Correct answer(s):

2. Detecting and correcting scope creep
4. Managing change requests to prevent detrimental changes to scope

2. Inputs for detecting scope problems

Sometimes the need to control scope arises from day-to-day monitoring and control activities. For example, when checking daily work performance data, you might detect scope creep or variance. Scope creep is the difference between work performance data and baseline information found in the project management plan. Both of these are inputs to the Control Scope process.

Select each subsidiary component of the project management plan to learn about the role each plays in controlling scope.

Scope management plan
The scope management plan describes how to manage and control a project's scope, including the process for developing the scope statement and WBS, as well as the responsibilities of everyone involved.
Scope baseline
The scope baseline consists of the project scope statement, the WBS, and the WBS dictionary. You compare it against work performance information to detect any variance. It also helps you explain the causes and predict the impacts of a variance.
Requirements management plan
The requirements management plan describes how to plan, track, and report changes to requirements, initiate them, analyze their impact, and approve them.

Two other subsidiary plans are used to control scope: the configuration management plan and the change management plan.

The configuration management plan defines the items, attributes, or project documents that must be controlled because they're integral to the project's success.

These items have been "configured" in a specific way that should not be changed without an approved change request.

Configurable project items include product design documents, the product and its components, project management documents and policies, and the results of quality and stakeholder reviews.

Select each type of configurable item to learn why it needs to be controlled.

Product design documents
Product design documents are configurable because they contain current information on how the product will perform and must be built. They are closely tied to the requirements for product features and functions.
The product and its components
The product, once it's being assembled, is configurable. It must conform to the design documents so it reflects exactly what is required. All components of the product must be built according to the scope.
Project management documents and policies
All project files and the documentation they contain about the project's scope, budget, and schedule, as well as all project guidelines and policies, are configurable. All these documents are of major importance to the project, and the Control Scope process must strictly control changes to them.
The results of quality and stakeholder reviews
The results of quality reviews contain vital information that assists in improving quality, and in ultimately producing the product to the scope requirements. Stakeholder reviews are records of the project's progress and milestones. Such information is critical when backing up claims for payment and when explaining decisions to the stakeholders.

The change management plan is the road map you follow when controlling changes. It provides details on the change control process to be used for the project. A change control process has three main stages: review the change request, decide what to do about it, and communicate the resolution.

Select each stage to learn about its role in helping to control change.

Review request
The project manager and the relevant stakeholders review change requests. A request must thoroughly explain all costs involved and be clear about the reasons for change. It must also explain how the request will be carried out, including its constraints. You need to consider the impact of the change and the possibility of not approving it. The review request stage ensures a change to a scope is only approved if its benefits outweigh its costs.
Decide what to do
The change control board usually decides what to do – whether they should approve or reject a change request. If the benefits outweigh the costs, it's likely that a change is accepted, or approved with modification. Alternatively, the decision can be deferred to a later date. By making a decision, the change control board accepts responsibility for the scope change. This is necessary because a scope change alters a project fundamentally.
Communicate resolution
After a decision is made, the project manager communicates the resolution to the stakeholders and the project team – the people who must implement the change. This is necessary to ensure that the change is implemented properly. An incomplete implementation of a scope change can cause more problems down the line.

Supplement

Selecting the link title opens the resource in a new browser window.

Job Aid

Access the job aid Change Control Process whenever you need to use the change control process on one of your projects.

Another input, work performance data, refers to the collected statistics and data on the status of the work to complete the deliverables. You measure work performance so you can compare the data against the scope baseline.

Graphic

Areas of data include cost, duration, and quality.

The work performance data that you use for scope control will relate to other Knowledge Areas, such as cost, duration, or quality performance. When you analyze the information, you may detect cost overruns, schedule slippage, or quality deficiencies.

In particular, you're looking for signs of scope creep – a situation in which more work has been done than was required or product features don't match the specifications.

Suppose you're managing a project for an outdoor equipment company. The scope of the project is to develop camping tents that can withstand extremely low temperatures. During prototyping, research assistants report that a special insulating outer shell needs to be developed using specific chemicals. The scope variance in this situation is the need to develop the special insulating shell.

Question

Match the Control Scope process inputs to the roles they perform in this project. Inputs may be used more than once and some roles may not have a match.

Options:

  1. Work performance data
  2. Project management plan

Targets:

  1. Contains the actual work results – in this case, the outstanding action item
  2. Specifies that the scope of this project is to work on enhancements to the existing system
  3. Details the specific requirements for the outcome of the project
  4. Details the procedures to follow to integrate a scope change into the project

Answer

Work performance data represents the actual work results that you measure against the scope baseline to detect scope creep. In this project, the outstanding action item represents scope creep, and it can be corrected by completing the action.

The project management plan, which includes the scope baseline, describes what work is required and what the project must achieve. In this case, it is to enhance the existing call center system.

The requirements management plan is a component of the project management plan. This would include any type of project and product requirements documentation that has been accepted and agreed upon by key stakeholders. Requirements documentation is often used to detect deviation in the agreed upon scope of the project or product.

The scope management plan contains this information. It is a subsidiary plan of the project management plan.

Correct answer(s):

Target 1 = Option A

Target 2 = Option B

Target 3 = Option B

Target 4 = Option B

3. Inputs for managing scope changes

The Control Scope process also uses two outputs of the Collect Requirements process: requirements documentation and the requirements traceability matrix.

Some key information is included in the requirements documentation:

Another input of the Control Scope process is the requirements traceability matrix.

This is a table that links project requirements to their origins, and to their progress throughout the project.

Graphic

A requirements traceability matrix shows the relationship between a user requirement and a functional requirement. In this case, the user requirement is that the software is for financial transfers and must be secure. The functional requirement is that the software must be 128 bit encrypted.

The matrix helps manage change requests by identifying related requirements that might have more detail or be impacted by the change.

Graphic

An additional user requirement is added to the requirements traceability matrix: key-stroke logging must be prevented. An additional functional requirement is that graphical text recognition by the user must be implemented.

Consider a project to create a web site that enables users to take an online career preference test and receive a career guidance report. The project scope statement describes the site's product scope. A designer wants to allow users to answer nonrandomized questions in the testing form. To control this major scope change, you investigate the origin of the requirement in the requirements documentation. Then you use the requirements traceability matrix to find other requirements that may be impacted by the change.

Graphic

The original product scope stated "The career guidance testing form must rate users' level of preference to keywords and description of tasks. The questions must be randomized."

Select each input to the Control Scope process to find out how to use it to control a scope change.

Graphic

The user requirement 2 states that "Users must be able to rate their level of preference, in response to seemingly random questions. This requirement comes from the expert advisory panel."

Functional requirement S10 states "The form must compute scores according to users' preferences. For the result to be accurate, the questions must appear randomized to the user. Randomized questions must allow user ratings from 1 to 5, inclusive."

Requirements documentation
The requirements documentation calls for the preferences form to have randomized questions. The requirement behind the randomization was specified by a panel of experts.

Requirements traceability matrix
You check the requirements traceability matrix, which explains why the randomization is necessary – so that the results of the test are more accurate. You reject the change request to have nonrandomized questions because it runs counter to a key requirement.

Organizational process assets are existing documents that guide, and sometimes supersede, the policies and procedures in the project management plan and its subsidiaries. There are at least two examples of organizational process assets that are inputs to the Control Scope process.

A company's formal and informal scope control-related policies, procedures, and guidelines help project managers standardize the way they modify, approve, and validate changes to a project's scope. They may also provide useful information on how scope was controlled successfully on previous projects.

A company usually has set monitoring and reporting methods that need to be used for all of its projects. These help project managers monitor variances in scope and communicate these to all relevant stakeholders when they occur.

Question

Refer to the learning aid Hospital Staff Training Project to help you answer this question.

Match the Control Scope process inputs – or components of inputs – to the roles they play in managing this scope change. Inputs may match to more than one role.

Options:

  1. Project management plan
  2. Work performance data
  3. Requirements traceability matrix
  4. Requirements documentation

Targets:

  1. Helps detect scope change by telling you the project must train 120 staff members in five months
  2. Helps you detect variance by informing you that only 15 people have passed the test
  3. Tells you that the training protocol is an item that requires strict control
  4. Describes the change control process you use to manage the change request and implement the change
  5. Tells you that the training protocol was designed this way to minimize costs
  6. Contains the project's objective to help you keep the project on track after the change

Answer

The scope baseline is a component of the project management plan. It enables you to determine whether there is a scope change by comparing the expected work results in the baseline with work performance data.

Work performance data provides the actual performance values that you measure against the expected performance in the baseline. If there is any variance, you will need to consider how to deal with it.

The configuration management plan is a component of the project management plan. It describes which project items are configurable, meaning they can only be changed by a formal change request.

The change management plan is a component of the project management plan. It outlines the decision-making process that you follow to ensure that change requests are handled correctly and that the resolution is communicated and implemented.

The requirements traceability matrix assists in controlling scope by indicating what the original requirement was. Sometimes the change request will conflict with this requirement.

The requirements documentation contains information, such as high-level project objectives, compliance requirements, and quality requirements, that helps you make decisions regarding change requests. In this case, the objective is to train the staff members in using the new workflow system.

Correct answer(s):

Target 1 = Option A

Target 2 = Option B

Target 3 = Option A

Target 4 = Option A

Target 5 = Option C

Target 6 = Option D

Question

Which of these examples are inputs – or components of inputs – to the Control Scope process?

Options:

  1. A plan that describes who is responsible for every part of the scope process
  2. A plan that describes how to manage a change in requirements
  3. Records that describe how scope was controlled on previous projects
  4. Existing policies and procedures that describe how to monitor and report change
  5. A description of activities that will prevent any form of change to a project's plans
  6. A description of the changes stakeholders want to implement

Answer

Option 1: This is a correct option. The scope management plan is a component of the project management plan. It lays out how the scope process is going to run, who is responsible for it, and what the project scope statement is. This information is a vital input to the Scope Control process, which aims to detect scope creep and manage change effectively.

Option 2: This is a correct option. The requirements management plan, which is a component of the project management plan, is an input to the Scope Control process. Among other things, it describes how requirements changes must be managed, to ensure that they're reviewed and implemented properly.

Option 3: This is a correct option. Organizational process assets are an input to the Scope Control process because they provide historical information on how scope was controlled on other projects.

Option 4: This is a correct option. A description of how to monitor and report change, such as an existing organizational policy on change control, is an example of an organizational process asset that is also an input to the Scope Control process. The project manager is guided by it in managing and communicating change to stakeholders.

Option 5: This is an incorrect option. All projects are subject to change; there are no activities that can prevent it. The Control Scope process helps you detect change and find ways to resolve it and limit its impact on the project. It also ensures that only beneficial changes are approved.

Option 6: This is an incorrect option. Change requests are an output of the Control Scope process. They result when the inputs have been analyzed and deviations between actual performance and the baseline have been found.

Correct answer(s):

1. A plan that describes who is responsible for every part of the scope process
2. A plan that describes how to manage a change in requirements
3. Records that describe how scope was controlled on previous projects
4. Existing policies and procedures that describe how to monitor and report change

4. Summary

The purposes of the Control Scope process are to control scope creep and changes to scope that would have a detrimental effect on a project.

The process involves identifying and analyzing variance from project plans, taking steps to bring scope back in line when necessary, and managing the impact of changes made. It also involves ensuring that all requested changes are processed through the Perform Integrated Change Control process.

The project management plan is one of the key inputs to the Control Scope process. It contains the scope baseline, scope management plan, change management plan, configuration management plan, and requirements management plan. Other inputs include work performance data, requirements documentation, requirements traceability matrix, and organizational process assets.

Back to top

Scope Variance Analysis

Learning Objective

After completing this topic, you should be able to

1. Identifying scope variance

Imagine you're running a project to lay a pipeline for a water supply firm. During a weekly inspection, you discover that a section of the piping was laid too close to a protected wetland area. The section needs to be moved, but this will increase costs and take up resources and time.

The Control Scope process gives you the tools to manage situations like this. You use variance analysis to monitor scope during daily monitoring and inspections.

Graphic

A flow diagram shows that variance analysis during the Control Scope process involves assessing and reviewing changes. Then a decision is made to approve, defer, or reject the change.

Monitoring scope is about measuring work performance and product features against the scope baseline. This way you can detect when more or less work than necessary is being done. You may also discover that the wrong features have been added to a product. You use variance analysis to identify the variance, look for the cause, assess the impact of the variance, and choose the appropriate response.

Graphic

For example, video capabilities may be added to a smartphone when it should only have e-mail, music capability, calculator, and calendar.

Being able to identify that a project is not staying within scope is not enough. You also need to identify the factors that are driving the project off course. Pinpointing the cause is an important step in solving the variance, and – where necessary – in creating the appropriate change request.

This involves some investigative work using the requirements documentation and the WBS dictionary. In particular, you look at the planned specifications for the work and the resource assignments for the work most directly related to the variance.

Graphic

An excerpt of a WBS dictionary template contains fields such as project name, date, WBS number and name, parent WBS number and name, person or organization responsible for the work, originating requirements number in the traceability matrix, scope of work, and child WBS name and number.

Suppose you've used the WBS dictionary to identify the person responsible.

Now you follow this up by asking this person to investigate the direct cause of the problem.

The cause may be human error, but it might also be a process gap or a mechanical fault.

For instance, you discover that the table top you manufactured is too long. So you use the WBS dictionary to find out who calibrated the machinery and the requirements documentation to find out the planned calibration. Then you investigate why the variance happened. It turns out that the machine's sensitive calibration dial was faulty. After having the dial serviced, the remaining products are manufactured to correct specifications.

Question

Suppose you're managing a project to upgrade the access control systems at a bank using the latest retinal scanning identification device. At an inspection, you find out that the scanner is malfunctioning. This represents scope variance.

How do you go about finding the cause of the variance?

Options:

  1. Find out from the WBS dictionary who was responsible for installing the device
  2. Ask the person who installed the device to investigate why it isn't working
  3. Contact the stakeholders and find out why they specified a device that malfunctions
  4. Adopt a "wait and watch" attitude, because the reason for the malfunction might be revealed in time
  5. Check the requirements documentation for the exact description of how the scanner is supposed to function

Answer

Option 1: This option is correct. You would first look in the WBS dictionary, at the resource assignments for the work, to find out who was responsible for the work.

Option 2: This option is correct. You would ask the person responsible for the work to study the problem and report back to you on its cause, whether mechanical fault or human error.

Option 3: This option is incorrect. You would not contact the stakeholders and hold them responsible for supplying a malfunctioning device. Even if the device is inherently flawed, this would be the manufacturer's responsibility, rather than that of the stakeholders.

Option 4: This option is incorrect. Sitting back and hoping that a problem will resolve itself is a recipe for disaster. You need to take a proactive approach and actively investigate the problem.

Option 5: This option is correct. In order to investigate variance, you need to know how the product is supposed to perform to be able to compare it to how the product is performing during inspection. The planned performance information is found in the requirements documentation.

Correct answer(s):

1. Find out from the WBS dictionary who was responsible for installing the device
2. Ask the person who installed the device to investigate why it isn't working
5. Check the requirements documentation for the exact description of how the scanner is supposed to function

A project manager must take all variances seriously – they indicate that something is wrong with the project or product development process, and needs to be addressed.

So once you've found the cause of a variance from the scope baseline, you need to assess its impact on the project's objectives.

You should correct a variance if it's impacting the objectives significantly, if it will become significant because of inaction, or if it's relatively small and easy to fix. Sometimes a variance is large but in an area or product feature that doesn't affect the business objectives. In this case, you might not need to fix it. But when the project or organizational objectives are seriously threatened, you definitely need to find an appropriate solution.

Suppose you're managing a project to design a new type of steel girder that's made with a lighter but more durable material. You identify a variance – the first batch of girders are an inch too narrow compared to industry standards.

Even before you investigate, you know the impact is serious – the specified width was the minimum allowed by industry regulations.

If the variance is not corrected, the project's objectives won't be met.

Reflect

Think of a project you've been involved in where you had to resolve scope variance and weigh the impacts of different solutions.

What were some of the trade-offs that you considered, and how did you eventually fix the problem?

Take a moment to reflect on this and then enter your ideas in the text box provided. Then select the Next Page button for more about finding solutions to variances.

Write down your response or enter it in a text file in your word-processor application (or in a text editor such as Notepad) and save it to your hard drive for later viewing.

You may have noted that once you've identified a variance and explained it, you evaluate the impacts of the available solutions before you choose the appropriate response.

This might mean a change in procedures to bring the project back in line with its planned scope.

Whatever solution you consider to correct scope variance, it will usually impact the budget, and possibly the schedule. In fact, these three elements form what project managers call the "triple constraint" model, in which a change in one element forces a change in one or both of the others. This model enables you to evaluate the possible solutions to a variance.

Graphic

The triple constraint model is illustrated using a triangle of equal sides, which represent the scope, schedule, and budget.

If you detect a scope variance that will create cost overruns to fix, you may need to consider reducing the scope.

Alternatively, you will have to request more funding in the form of a change order on the budget.

The option of changing the schedule to fix a scope variance won't usually work – the schedule didn't create the mistake, and extending it will just increase costs.

Question

Consider the "triple constraint" model.

How does this model assist you in analyzing a scope variance?

Options:

  1. It illustrates the relationship between scope, schedule, and budget – a change to one will affect the other
  2. It helps you consider how a possible solution will impact the project
  3. It represents the independence of scope, schedule, and budget considerations
  4. It enables you to estimate the cost in dollars of various corrective options

Answer

The triple constraint model illustrates how a change in one element impacts one or both of the other elements.

Correct answer(s):

1. It illustrates the relationship between scope, schedule, and budget – a change to one will affect the other
2. It helps you consider how a possible solution will impact the project

When a project approaches its deadline and time for completing work runs out, scope variance can result. In this case, one option is to spend more to complete the work on time by expanding the budget. For example, you might increase funds to hire extra technicians to get the job done by the deadline.

You may experience a project in which you detect variance close to the "drop-dead date."

And perhaps the budget's almost used up and you can't afford to fix the variance.

In this case, you might find resources within the project or organization that can come to the rescue.

This is known as stacking resources. For a software development project that is in trouble because time and money have run out, you might, for instance, find expert developers within the organization who can be reassigned to sort the problem out without incurring extra costs.

Question

Access the learning aid Cabinet Manufacturing Project to review the details of a project to help you answer the question.

Considering the impact of the variance and the available options, which of these actions do you recommend?

Options:

  1. Buy different, cheaper timber to complete the project
  2. Use some of the budget to transport the available timber from the warehouse to the project site

Answer

Changing materials to resolve the variance is not an option. The scope called for a specific material, and this was a key requirement. The most viable solution is to use available funds to transport the available resources to the project site.

Correct answer(s):

2. Use some of the budget to transport the available timber from the warehouse to the project site

Once the project manager has assessed and rejected possible ways to correct a variance, the only other option is to change a project's scope. This means either not fixing the variance in question, or fixing it at the expense of reducing the scope in another part of the project. Either way, this will always require a scope change request.

In a change request, you include the results and conclusions of your investigation into the variance and explain how you derived them.

A change request is always subject to review, usually by the change control board, as described in the project's change control process.

If it is approved, the change is implemented through the Perform Integrated Change Control process.

Consider a project to develop a software package that the sales staff for a bathroom design company will use during sales calls.

The software includes a graphic design module to aid in designing bathrooms to customers' specifications.

It can also generate a quotation on the spot, based on the customer's choices. Giving the customer the design and quotation at once should lead to more successful sales.

The development schedule is fixed because the new sales force needs to start training on the software urgently, but the budget is quite flexible. At an inspection, testing reveals some variances – bugs in the code that prevent the design module from working.

You analyze the problem and determine that the cause lies with an inexperienced developer.

The variances you've detected are serious because they directly impact the business benefits of the project. Time is running out and you need a solution.

So you draw on the budget to hire an expert developer to fix the bugs, thereby solving the variance problem.

Case Study: Question 1 of 3

Scenario

For your convenience, the case study is repeated with each question.

You discover a scope variance while working as a project manager installing a high-speed network. The project is ahead of schedule, so you have some time to resolve the variance and still meet its objectives within the scheduled time.

Access the learning aid High-speed Network Project to review the project's details.

Answer the questions in the given order to determine what needs to be done about the scope variance.

Question

You know that the project is underperforming. Before you can do anything about this, you first need to measure and explain this variance.

What information in the scenario will enable you to do this?

Options:

  1. Data transfer speeds are not satisfactory, and the requirements state the specified speeds and server configurations
  2. The project has a one-month time frame
  3. The budget is flexible and divided between installation and testing
  4. The project employs five senior network technicians
Answer

Option 1: This is the correct option. This information represents work performance data for the project. You consult the requirements documentation to view the specified speeds and server configurations, which you'll use to measure the shortfall in speed and test ideas about the cause of the variance.

Option 2: This option is incorrect. The project is a week ahead of schedule, so the schedule is not the cause of the variance. In this case, information about the schedule does not help you measure or explain the variance.

Option 3: This option is not correct. The problem that you've identified is related to data transfer speed. You can't use budget information to calculate the variance, and there is no indication that the budget is responsible for the shortfall in the speed.

Option 4: This option is incorrect. Information about the human resources of the project will not help you measure the variance, nor will it explain the speed shortfall in this case.

Correct answer(s):

1. Data transfer speeds are not satisfactory, and the requirements state the specified speeds and server configurations

Case Study: Question 2 of 3

Scenario

For your convenience, the case study is repeated with each question.

You discover a scope variance while working as a project manager installing a high-speed network. The project is ahead of schedule, so you have some time to resolve the variance and still meet its objectives within the scheduled time.

Access the learning aid High-speed Network Project to review the project's details.

Answer the questions in the given order to determine what needs to be done about the scope variance.

Question

Now you need to assess what action to take.

What information in the scenario assists you in assessing the impact of the variance?

Options:

  1. The center has a reputation to uphold of providing top computing facilities
  2. The network must be able to handle complex parallel processing functions
  3. The network technicians worked as a team on the entire project
  4. The budget is constrained, so there is limited funding to analyze and resolve the problem
Answer

Option 1: This is a correct option. The impact of not meeting the project scope specifications is serious for the organization, because it will impact the center's reputation of providing excellent computing facilities.

Option 2: This option is correct. This is the high-level objective that gave rise to the need for the network speed requirements. Failing to reach the required speed will seriously impact this objective.

Option 3: This is an incorrect option. The operational procedures that the project team used are not relevant in assessing the impact of the variance.

Option 4: This option is incorrect. The budget in this scenario is flexible, so there is funding available to analyze and resolve the problem.

Correct answer(s):

1. The center has a reputation to uphold of providing top computing facilities
2. The network must be able to handle complex parallel processing functions

Case Study: Question 3 of 3

Scenario

For your convenience, the case study is repeated with each question.

You discover a scope variance while working as a project manager installing a high-speed network. The project is ahead of schedule, so you have some time to resolve the variance and still meet its objectives within the scheduled time.

Access the learning aid High-speed Network Project to review the project's details.

Answer the questions in the given order to determine what needs to be done about the scope variance.

Question

After investigating, you discover that the specified server operating system is not capable of managing the extreme speeds of the network, which is resulting in the speed shortfall. Finally, you need to choose an appropriate solution to the variance.

Which solution is viable, given the project's scope, budget, and schedule, and the causes and impacts of the variance?

Options:

  1. Submit a change request to use a server operating system capable of handling a network of this size
  2. Utilize the flexible budget to purchase the required operating system
  3. Request a reduction in the required network speed
  4. Suggest an extension in the schedule of one month
Answer

Option 1: This option is correct. In this case, the need for a scope change is indicated. This must be handled via a change request, which will be processed through the project's Integrated Change Control process.

Option 2: This option is correct. The budget of the project is flexible, so it's viable to use it to resolve the variance.

Option 3: This option is incorrect. The specified speed is a scope constraint that can't be changed.

Option 4: This option is incorrect. The schedule isn't flexible in this example, and there's no reason to extend it.

Correct answer(s):

1. Submit a change request to use a server operating system capable of handling a network of this size
2. Utilize the flexible budget to purchase the required operating system

In the high-speed network project, you successfully identified and explained the variance using work performance data, as well as information in the requirements documentation.

You identified the cause of the variance – a shortcoming of the server operating system. The appropriate solution – replacing the operating system – required a scope change.

So you filled out and submitted a change request, detailing your analysis of the variance, including its causes and impacts.

Supplement

Selecting the link title opens the resource in a new browser window.

Learning Aid

Use the learning aid High-speed Network Change Request to review the details that went into the change request.

2. Summary

Variance analysis involves comparing actual work performance information against the scope baseline. You also use variance analysis to discover the cause of a variance, the impact it has on the project, and the impact of any corrective action you might take.

The impact of a variance is determined by the triple constraints of scope, budget, and schedule. Solving scope variance usually involves some form of compromise, or trade-off, between these constraints.

If you're unable to resolve a significant variance in scope, or if the stakeholders and sponsor request a change that would improve project results, you need to create a change request that contains the details from the variance analysis.

Supplement

Selecting the link title opens the resource in a new browser window.

Follow-on Activity

Use the follow-on activity Using Scope Variance Analysis to apply your skills and knowledge to a case of variance that you've experienced in a project.

Back to top

Outputs of the Control Scope Process

Learning Objective

After completing this topic, you should be able to

1. Control Scope outputs

Do you know the quickest way to lose control of a project? Allow arbitrary changes to the original project plan to go unchecked. By closely monitoring the project and controlling changes, you can get your entire team and stakeholders working toward the same goal – delivering the project on time and within budget.

One of the most important outputs of the Control Scope process is change requests. Other outputs include updates to the project management plan, work performance information, project documents updates, and updates to organizational process assets.

Select each Control Scope output to learn more about it.

Change requests
Controlling scope may result in change requests from time to time. The scope baseline or other project baselines, such as the schedule or budget, may need to be updated to control project performance. As an output of this process, change requests become inputs to the Perform Integrated Change Control process.
Work performance information
Work performance information reflects the results of comparing actual performance data to planned performance in the project baselines, especially those for scope, cost, and time. It may include summaries of the changes made, the sources of the changes, or how they impact schedule or cost.
Project documents updates
Some of the documents that may need to be updated are the requirements documentation and the requirements traceability matrix. The requirements documentation describes how a project's requirements meet a business need. The matrix links the requirements to the need and helps trace its development throughout the project's life cycle. Ensuring that both documents are up to date helps manage and control changes to a project's scope.
Updates to organizational process assets
Organizational process assets are any information that can affect a project's success. In addition to policies, guidelines, and manuals, these assets also include all project documentation and records, and lessons learned from previous projects. For instance, suppose you change the scope of a project to utilize a new machine in the production process in order to manufacture a product more efficiently. The operating manual of the machine and the updated production process guidelines become new organizational process assets.
Project management plan updates
Since the project management plan contains all the project baselines, it will need to be updated if controlling scope has resulted in changes to components of the scope baseline – such as the scope statement or WBS – or to any other baselines.

Suppose you're managing a food technology research project to develop healthy new food flavorings. The original scope required the researchers to perform simple chemistry tests of acidity, salt, and sugar content. Midway through the project, the client decides to upgrade the scope to include a chemical analysis of the vitamin, mineral, and amino acid content of each ingredient. You create a change request to capture this information.

Among the changes you make to elements of the project management plan, such as a small budget increase, you update the testing protocol.

Graphic

The testing protocol was developed on January 15, and the contents page shows three sections: Acid tests, Salt tests, and Sugar tests.

Instead of describing just the simple tests, it now includes a complex procedure involving new methods of testing, analyzing, and reporting results.

Graphic

The revised testing protocol testing for vitamins, minerals, and amino acids. Within each group, there are new methods, equipment, and ways of reporting the test results.

You update the organizational process assets and make a note of the new units to use for testing the vitamin, mineral, and amino acid levels.

You pull together information about how work performance may be impacted by this change, and instruct the research team to go ahead with the new testing.

You also update the requirements documentation and the requirements traceability matrix with specifications for the new chemical analyses.

Question

Access the learning aid Emissions Control Project to help you answer this question.

Which outcomes represent outputs of the Control Scope process?

Options:

  1. You update the scope management plan and other impacted components of the project management plan
  2. You summarize information regarding how the change will affect the schedule and project costs
  3. You create a change request and submit it to the change control board for approval
  4. You submit another change request to add an extra ten byproducts to the project's monitoring activities, to stay ahead of the legislation
  5. You carry out a scope variance analysis
  6. You make necessary updates to the requirements documentation and any other documents affected by the new legislation

Answer

Option 1: This is a correct option. When a scope change is approved, you update the project management plan to reflect any additional information that's become available. In this case, the new compliance legislation is critical to the project, so you add it.

Option 2: This option is correct. The stakeholders should be brought up to date, so it's important to summarize information and report to them. Work performance information in this case may reflect how you expect adding the extra byproducts will affect project baselines.

Option 3: This option is correct. Change requests are an output of the Control Scope process.

Option 4: This option is incorrect. Although you might feel strongly that it's worth expanding the project's monitoring activities to keep one step ahead, you would not do so. For budgetary reasons, the project must not go beyond what is specified in the legislation.

Option 5: This option is incorrect. Variance analysis is not an output of the Control Scope process, but rather it is the technique used by Control Scope to determine the cause and degree of variance from the original scope baseline.

Option 6: This option is correct. Updated project documents are outputs of the Control Scope process. These documents need to be accurate moving forward in order to properly carry out further monitoring and control activities.

Correct answer(s):

1. You update the scope management plan and other impacted components of the project management plan
2. You summarize information regarding how the change will affect the schedule and project costs
3. You create a change request and submit it to the change control board for approval
6. You make necessary updates to the requirements documentation and any other documents affected by the new legislation

2. Summary

Changes to project scope impact costs, the schedule, or both, as well as most other areas of project management. That is why updates to the project management plan, other project documents, and organizational process assets are outputs of the Control Scope process. Change requests and work performance information are also outputs of this process.